Gamatronic Electronic Industries Ltd.
User Guide
Page 35
µ
PS Series 3:3 Phase 10kVA (GEMS)
3.
Turn
ON
the
BATTERY C.B.
on the back of the UPS. The
BATTERY C.B.
should be in a
vertical position.
BATTERY C.B. in ON position
4.
The UPS performs a self-test that takes approximately 1 minute.
Verify that the UPS OFF message is displayed on the LCD display
panel after the self test is completed.
5.
Wait approximately 40 seconds for “UPS OK” to appear on the LCD
display panel.
•
Verify that the green INV LED is lit on the control
panel.
•
If there is no mains or bypass input, “INPUT FAULT”
appears on the LCD display panel.
•
If the bypass condition is normal, the green bypass
LED is lit on the control panel indicating that the
bypass function is ready for operation.
(Note: The bypass display will show current values only
when the B/P function is activated.)
•
To switch the load to bypass mode, press the B/P
button on the control panel 2 times.
•
To return to the inverter output, press the INV button.
(See Section
5.3)
B/P BUTTON
INVERTER BUTTON
Figure 19: Inverter and B/P Buttons