Instruction Manual
Top & Bottom Loading Arms
E2110, E2112, E2022, E2025
E2033, E2304, E2573, E2123,
E2313, E2121
- 11 -
Length from the manhole. Return the loading arm to its parking position and
secure.
Note
Product remaining in the pipe might damage the swivel joints.
Drain the arms completely before returning to parking position.
8.2 Operation of the Loading Arms with Flange/Coupler
This section describes how to operate the loading arms with Dry-Break couplers
or flange connections on drop tube.
Remove the loading arm from its parking position and move to the tanker.
Connect the B-Length to the connection point at the tank. Make the appropriate
connection for end fitting.
The loading arm is now ready for loading. The loading process is defined by the
customer.
When the loading process has finished, close appropriate valve. Let arm drain if
required and disconnect the B-Length from the tank. Return the loading arm to its
parking position and secure.
9 Service and Maintenance
9.1 Safety Comments
A.
EMCO WHEATON recommends using EMCO WHEATON Service to maintain
the equipment.
B.
Only persons who are able to perform all tasks professionally due to their train-
ing and qualification are allowed to repair the loading arm (e. g. electricians for
the electrical system). Contact EMCO WHEATON if the loading arm is severely
damaged.
C.
Secure the loading arm while performing maintenance tasks to avoid it from
moving unexpectedly.
D.
Take special care and use adequate hoisting devices (cranes, belts) when lifting
heavy components when performing maintenance tasks.
Warning
Severe injury or death could result if the
product leaves the loading arm under
high pressure or if you open hydraulic
lines.
Purge the loading arm and depressurize
lines when servicing any components of
the loading arm.