15. TESTING PROCEDURES FOR QC AFTER INSTALLATION
15. TESTING PROCEDURES FOR QC AFTER
INSTALLATION
After the installation has been completed, it is necessary to test the following to ensure that the
SR-1000 has been properly installed:
1. Test the video playback capabilities of the SR-1000.
2. Test the audio playback capabilities of the SR-1000 and verify that all the channels are
working. Also check for any static noises.
3.
Test the server’s ability to activate automation cues using test cues for lights, curtains, sound
and fire alarm.
4. Test the remote access capabilities of the server, including: Theater Management System
(TMS) access and network connectivity.