SitePro 10-15-20-30-40 kVA / S8
5 INSTALLATION
5.1 TRANSPORT
The UPS is packaged on a pallet suitable for handling
with a forklift.
Pay attention to the
centre of gravity
.
The UPS must be moved in
upright position
.
Do not tilt cabinets
more than +/- 10°
during handling.
Move the UPS in it’s original package to the final destination
site.
Do not stack other packages on top
: the upper side of the
cabinet could be damaged.
If the UPS must be lifted by crane, use suitable lifting straps
and spreader bars.
Note of the centre of gravity marked on the package.
Take all necessary precautions to avoid damage to the
cabinet while hoisting the UPS
.
Forklift
Crane
Fig. 5.1-1 UPS cabinets moving
NOTE !
Check for sufficient floor and elevator
loading capacity.
5.1.1 Dimensions and weights
Dimensions
SitePro 10, 15, 20, 30 and 40 kVA
(W x D x H)
SP_010-0
40_S8_U
PS dimen
sions_GE
_01
1
'450
m
m
57.
08"
680mm
26.77"
800mm
31.49"
680 x 800 x 1450 mm
26,77 x 31,49 x 57,08 inches
Weight
SitePro 10, 15, 20, 30 and 40 kVA
UPS Model
Weight
without battery
Kg / lbs
Floor loading
kg /m
2
- lbs/sq.ft
Weight
with battery
Kg / lbs
Floor loading
kg /m
2
- lbs/sq.ft
SitePro 10 kVA
285 / 629
524 / 108
10Ah: 408 / 900
750 / 154
SitePro 15 kVA
285 / 629
524 / 108
17Ah: 480 / 1’059
883 / 181
SitePro 20 kVA
285 / 629
524 / 108
17Ah: 480 / 1’059
883 / 181
SitePro 30 kVA
340 / 750
625 / 129
24Ah: 610 / 1’345
1’122 / 230
SitePro 40 kVA
340 / 750
625 / 129
33Ah: 700 / 1’544
1’287 / 264