4.5.1 LP 3/5/6-11: standard installation procedure
If a battery extension pack is to be installed, please proceed with section 4.5.2.
If 2, 3 or 4 parallel operating units will be installed, please proceed with section 4.5.5.
The numbers between (brackets) refer to figure 12 in section 5.1.
BATTERY
DISCONNECTED
EMERGENCY
SHUTDOWN
stand-alone
and RPA card
available
see 4.5.5 / 7.3
see 6.3-4
10
9
8
7
6
5
4
3
2
1
1. Make sure that all circuit breakers (7-8-9) are in ‘off’
position (down).
2.
Loosen the 3 screws and remove the metal cover (11)
of the I/O terminals.
3. Lead the input/output cables through the swivels of
the metal cover (11).
4. Input (11a). Connect the mains supply wires to the
terminals 2 (Line) and 3 (Neutral) and the ground wire
to terminal 1. Ground connection is essential!
5.
Output (11b). Connect the load wires to the terminals
4 (Line) and 5 (Neutral) and the ground wire to
terminal 6. Ground connection is essential!
6. Re-install the metal cover (11). Fasten the cables in the
swivels.
Insert the battery fuse in the fuse holder (17)
and close the fuse holder.
7.
An emergency shutdown switch can be connected to
connector J3 on the RS232/Contact Interface Card,
between pins 3 and 4. See section 6.2 for more
information.
8. For advanced communication possibilities, the
RS232/contact interface port (12a) can be connected
to a computer system. See section 6.1 for more
information. *
9.
The middle ‘option slot’ (13) allows easy installation of
plug-in cards: SNMP Card or Relay Card. See
sections 6.3 and 6.4 for more information. *
10. The right ‘option slot’ (14) allows easy installation of
the RPA-card (Redundant Parallel Architecture). If the
card is already mounted, and if the unit is intended to
be used stand-alone, a bus terminator (delivered with
the unit) has to be placed in one of the two bus
connectors on the card. If the unit will be part of a
parallel system, see sections 4.5.5 and 7.3 for more
information. *
*
The data cables can be attached to the cabinet with
tie-wraps, position the tie-wraps in the small holes
(18) underneath the option slots.
11. Connect the utility power to the UPS.
Figure 6. LP 3/5/6-11:
Standard installation procedure
12. For a quick start proceed with section 5.2 ‘Start-up’.
OPM_LPE_11X_3K0_10K_1GB_V041
9
GE DE LP 11 UPS: User manual 4.1 (GB)