GE Zenith Controls, Inc.
830 West 40th Street Chicago, IL 60609 / Telephone: (800) 637-1738
rev 9-5-2012
GE Digital Energy
Power Quality
Y
N
NA
1
Verify that IMPORTANT SAFETY INSTRUCTIONS (Section 1) have been
reviewed.
2
Verify that the UPS is carefully unpackaged, inspected for damage, and
placed near the installation location.
3
Verify the proper size wires and circuit breakers are utilized.
4
Verify the proper input voltage installation procedures for 208-240vAC or
120vAC input are used to connect the UPS.
a. 4.4.1.1 Standard installation procedure: Vin 208-240Vac,
Vout 120/208/220/230/240Vac
b. 4.4.1.2 Installation procedure: Vin 120Vac (optional
5/6kVA), Vout 120/208/220/230/240Vac
Proper input voltage is connected to include the system ground
4
Referring to the following sections of the installation / user manual,
perform the hardware modifications required for the input voltage to be
applied.
1. 4.4.2 Available input voltages: hardware modifications
2. 4.4.2.1 Input voltage 208 or 240Vac
3. 4.4.2.2 Input voltage 120Vac (optional, 5/6kVA only)
5
Referring to the following sections of the installation / user manual,
perform the hardware modifications required for the output voltage
necessary for the critical load.
1. 4.4.3 Available output voltages: hardware modifications
2. 4.4.3.1 Output voltage 208Vac
3. 4.4.3.2 Output voltage 120Vac split-phase
4. 4.4.3.3 Output voltage 220/230/240Vac
5. 4.4.3.4 Output voltage 120Vac single phase
6
Referring to the following section of the installation / user manual, perform
the software modifications required for the input and output voltage
associated to any hardware modifications performed above.
4.4.4 Input / output voltages: Software modification
7
Referring to the following section of the installation / user manual, perform
the installation of the external battery pack(s).
4.4.5 Installation of GE Digital Energy LanPro-U battery extension pack(s)
8
Referring to the section 4.4.6 LanPro-11U series: 2 / 3 / 4 parallel
operating units – additional info, contact GE Power Quality service with
any questions on the installation of a parallel system.
8
Referring to the section 5 of the installation / user manual, verify proper
operation of the GE LP11-U UPS.
If you have any questions or need to request onsite service, please contact us at 800-637-1738
(Option 3).
Thank you for your business.