3.6 UNPACKING
Move the equipment in it’s original packing, carton box or wooden case, until the place of
installation and remove the packing and the transport sockets only just before installing the UPS.
1
Procedure for the unpacking of the UPS:
•
Make sure to have sufficient space around the
UPS before you start unpacking.
•
Cut the two straps
“
A
”
fixing the carton box.
2
•
Remove the wooden top cover
“
B
”
, which will be
used as a ramp and position it as shown in the
picture.
•
Remove the protection
“
C
”
outside the cabinet
and the accessories bag.
•
Remove the carton box
“
D
”
.
3
•
Remove the 2 angle irons
“
E
”,
which are fixing the
UPS to the wooden base
“
G
”
by unscrewing bolts
“
F
”
.
4
•
Push now the UPS towards the ramp
“
B
”
and let it
slide down the ramp.
This has to done with the utmost care!
Fig. 3.6-1
LP 33
unpacking sequence
NOTE !
Be aware of the heavy weight of the
UPS, in particular if already equipped