FVP 110 Fieldbus Valve Positioner Manual
10
GE Energy
Insulation Resistance Test and Withstand Voltage Test
CAUTION
Overvoltage of the test voltage is so small that it does not
cause an dielectric breakdown but can deteriorate insulation
and lower the safety performance; to prevent this, keep the
amount of testing to a minimum.
The voltage for the insulation resistance test must be 500V
DC or lower, and the voltage for the withstand voltage test
must be 500V AC or lower. Failure to heed these guidelines
may cause faulty operation.
Where a built-in arrester is provided (suffix code: /A), the
voltage for the insulation resistance test must be 100V DC or
lower, and the voltage for the withstand voltage test must be
100V AC or lower. Failure to heed these guidelines may
cause faulty operation.
Follow the steps below to perform the test, the wiring of the communication line must be
removed before initiating testing.
Insulation Resistance Test Procedure
1. Lay transition wiring between the + terminal and the
-
terminal
.
2. Connect the insulation resistance meter (with the power turned OFF) between the
transition wiring of Step 1 and the ground terminal. The polarity of the input terminals
must be positive and that of the ground must be negative.
3. Turn the power of the insulation resistance meter ON and measure the insulation
resistance. The duration of the applied voltage must be the period during which 100
M
Ω
or more is confirmed (or 20 M
Ω
if the unit is equipped with a built-in arrester).
4. Remove the insulation resistance meter, connect a 100 k
Ω
resistor between the
transition wiring, and allow the electricity to discharge. Do not touch the terminal with
your bare hands while the electricity discharges (one second).
Withstand Voltage Test Procedure
Testing between the input terminals and the grounding terminal:
1. Lay the transition wiring between the + terminal and the - terminal, and connect the
withstand voltage tester (with the power turned OFF) between the transition wiring
and the grounding terminal. Connect the grounding side of the withstand voltage
tester to the grounding terminal.
2. After setting the current limit value of the withstand voltage tester to 10 mA, turn the
power ON, and gradually increase the voltage from 0 V to the specified value.
3. Maintain the voltage at the specified value for one minute.
4. On test completion, carefully reduce voltage to avoid voltage surge.
Summary of Contents for FVP110
Page 14: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 22: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 48: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 50: ...FVP 110 Fieldbus Valve Positioner Manual 34 GE Energy Block Diagram Figure 14 Block Diagram ...
Page 74: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 88: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 97: ...81 Dimensions Standard Specifications Dimensions Figure 46 Single Acting Actuator Dimensions ...
Page 99: ...83 Dimensions Standard Specifications Figure 48 Terminal Configuration ...
Page 100: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 115: ...99 View Object Configuration Table 11 View Object for Transducer Block continued ...
Page 117: ...101 View Object Configuration Table 18 View Object for AO Function Block ...
Page 119: ...103 View Object Configuration Table 20 View Object for OS Function Block ...
Page 121: ...105 View Object Configuration Table 22 View Object for Resource Block ...
Page 124: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 130: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 138: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 156: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 168: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 238: ...FVP 110 Fieldbus Valve Positioner Manual 222 GE Energy Table 72 LM Parameter Part List ...
Page 239: ...223 LM Parameter List Link Master Functions ...
Page 246: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 262: ...FVP 110 Fieldbus Valve Positioner Manual 246 GE Energy Table 85 Download Error Codes ...
Page 265: ...249 Comments on System Network Software Download Table 88 DOMAIN_DESCRIPTOR ...
Page 266: ...FVP 110 Fieldbus Valve Positioner Manual 250 GE Energy Table 89 DOMAIN_HEADER ...
Page 288: ...FVP 110 Fieldbus Valve Positioner Manual This page intentionally left blank ...
Page 289: ...273 H Customer Maintenance Parts List ...
Page 290: ...FVP 110 Fieldbus Valve Positioner Manual 274 GE Energy ...
Page 291: ......