49
07 Equipment Commissioning
User Manual
V1.0-2023-10-30
7�2 Power On
7 Equipment Commissioning
7�1 Check Before Power ON
No�
Check Item
1
The product is firmly installed at a clean place that is well-ventilated and easy-to operate.
2
The PE, DC input, AC output, and communication cables are connected correctly and
securely.
3
Cable ties are intact, routed properly and evenly.
4
Unused cable holes are fitted using the waterproof nuts.
5
The electrical conduit holes are sealed.
6
The voltage and frequency at the connection point meet the inverter grid connection
requirements.
Single Inverter
Turn on:
1
2
3
4
ON-GRID
AC breaker
Utility meter
PV string
Battery
Battery breaker
Utility grid
Load
BACK-UP AC breaker
Only for Australia.