3. Fix the earth wire shall on the machine, illustrated as the below figure.

4. In order to improve the corrosion resistance of the terminal, it is recommended to apply silica 

gel on the earth terminal for the corrosion protection after the grounding cable assembly is 
completed.

4.3.4 Connecting Inverter To PV Panel 

Caution

Make sure the DC switch is turned off before connecting PV string to the inverter.

Make sure PV string polarity confirms with DC connector, otherwise, it will damage the inverter.

Make sure the maximum open circuit voltage (Voc) of each PV string does not exceed the 
maximum input voltage of the inverter under any condition(1100V).

Make sure that the maximum short circuit current of each DC input is less than the inverter 
allowable limit.

Do not connect positive or negative pole of PV string to earth (PE terminal). Otherwise, it will 
permanently destroy the inverter.

Positive wire shall be red, negative wire shall be black.

The minimum insulation resistance to ground of the PV panels must exceed 33.7kΩ

there is a risk 

of shock hazard if the requirement of minimum resistance is not met.

The GEP series has three PV input area PV1 input, PV2 input, PV3 input, each with MPPT 
tracker, therefore the three PV input can be different with each other, including different type of 
modules, different numbers of connecting PV strings, different orientation angel of PV modules.

There are four types of DC connectors, DEVALAN, MC4, AMPHENOL H4  and QC4.10 series. 

 

NO.

A

B

C

Name

Cold-pressed terminal

Screw

Yellow and green line

Explanation

M5*12

10~16mm

2

 

Inverter side

Positive Plug

Negative Plug

PV TOOL

A

B

C

Please use special tools to do crimping

MC4 & QC4.10

Negative connector

Positive connector

Inverter side

DEVALAN SERIES

MC4 SERIES

AMPHENOL SERIES

QC4.10 SERIES

Note: The actual DC connector used is as shown in the accessory box.

DC cable specification:

Value

4~5mm

2.5~4mm

2

About 7mm

Label

A

B

C

Description

External diameter of wire stock

Cross-sectional area of conductor material

Length of bare wire

A

B

C

The installation method of DC connector is shown in the two figures below.

In order to better dustproof and waterproof 
the internal inverter, all the DC connectors 
provided by accessory bag should be 
connected to the inverter. If only some of the 
DC connectors are used, the DC connectors 
without connection should be blocked with 
non-conductive insulator.

Plug with PV waterproof plug

Summary of Contents for GEP12-L-10

Page 1: ...UAL Global Sales Service Network GE is a registered trademark of General Electric Company and is used under license by GoodWe Technologies Co Ltd No 90 Zijin Rd New District Suzhou 215011 China www ge...

Page 2: ...7 5 System Operation 21 5 1 LCD Panel And LED 21 5 2 User Interface Introduction 22 5 3 System Configuration 25 5 4 Precaution For Initial Startup 30 5 5 Setting Inverter Parameters via App 31 5 6 Mon...

Page 3: ...work All detailed work related safety warnings and notes will be specified at the critical points in corresponding chapter All installation and electrical work must only be performed by qualified per...

Page 4: ...ons which will lead to potential injury to people and damage to inverters Static electricity may damage electronic components Appropriate method must be adopted to prevent such damage to the inverter...

Page 5: ...ter provides standard interface RS485 WIFI for communication Inverters also provide running recode data display parameter configuration via LCD panel For the main block diagram please refer to chapter...

Page 6: ...ommunication Terminal Grounding Screw Expansion Bolt Safe Screw Connecting Terminal Grounding AC Cover OT Terminal Insulation Sleeve WiFi Module WiFi communication Or without LCD Quick Installation In...

Page 7: ...values The Upward part The downward part The front part Both sides Interval 200mm 500mm 500mm 600mm 1200mm 500mm 1200mm 600mm 600mm 500mm 300mm The Upward part The downward part The front part Both si...

Page 8: ...low these steps to connect the utility and inverter 7 If the diameter of the cable does not match the terminal or if the cable is aluminum cable please contact after sales service Two mounting holes i...

Page 9: ...et of a suitable length with a wire stripper Output Current 31 5A 40A 54 5A 40A 43 3A 48A 53 3A 80A 96A 80A 96A Inverter Model GEP12 L 10 GEP15 L 10 GEP20 L 10 GEP25 10 GEP29 9 10 GEP30 10 GEP36 10 GE...

Page 10: ...not met The GEP series has three PV input area PV1 input PV2 input PV3 input each with MPPT tracker therefore the three PV input can be different with each other including different type of modules di...

Page 11: ...zlogger Pro manual Remote shutdown is only for European installations in compliance with European safety requirements A remote shutdown device is not provided by manufacturer DRED should be connected...

Page 12: ...ion This function is only applicable for WiFi model for specific configurations please refer to WiFi LAN Configuration Instruction in the attachment and you can also refer to the description of Demo V...

Page 13: ...ive On Fault occurred OFF No fault Status Indicator Green green green red light respectively corresponds to 5 2 User Interface Introduction Communication information icon GPRS and WiFi show the signal...

Page 14: ...Fi 22 93 3kWH 4 E TOTAL E DAY 01 01 2020 00 00 00 CARBON Fault Utility Loss 0 0kWH Basic Advanced WiFi 22 105 3kWH 4 E TOTAL E DAY 01 01 2020 00 00 00 Fault WiFi Con guration 22 Basic Advanced 01 01 2...

Page 15: ...0 00 Fault Country Code Holland Northlreland ChinaHigher France 50Hz France 60Hz WiFi 22 01 01 2020 00 00 00 Fault Language WiFi 22 01 01 2020 00 00 00 Fault Data Time WiFi 22 01 01 2020 00 00 00 Faul...

Page 16: ...i 22 01 01 2020 00 00 00 Normal Adv Settings HVRT Grid Type Password Factory Data Reset WiFi 22 01 01 2020 00 00 00 Normal Adv Settings HVRT Grid Type Password Factory Data Reset WiFi 22 01 01 2020 00...

Page 17: ...0 6 0 4 0 2 0 4 6 8 10 12 14 16 18 20 Month Year Basic Advanced 01 01 2020 00 00 00 Fault WiFi Con guration 22 Basic Advanced 01 01 2020 00 00 00 Normal WiFi Con guration 22 01 01 2020 00 00 00 Norma...

Page 18: ...local service office 1 Disconnect the DC switch take off DC connector check PV string voltage check if it exceeds the input voltage in inverter specification 2 If it does please reconfigurate PV panel...

Page 19: ...ber of MPP Trackers Number of Strings per MPPT Output AC Nominal Output Power W Nominal Output Apparent Power VA Max AC Active Power W Max AC Apparent Power VA Nominal Power at 40 W Max Power at 40 In...

Page 20: ...rent A Max Output Fault Current Peak and Duration A ms Inrush Current Peak and Duration A us Nominal Output Current A Power Factor Max Total Harmonic Distortion Efficiency Max Efficiency Europen Effic...

Page 21: ...T Output AC Nominal Output Power W Nominal Output Apparent Power VA Max AC Active Power W Max AC Apparent Power VA Nominal Power at 40 W Max Power at 40 Including AC Overload W Nominal Output Voltage...