6.9
Installing the Pole Columns
The operations described in this section must be carried out in se-
quence for each of the three pole columns. The poles themselves
can be installed in any order desired.
6.9.1
Erecting the Pole Columns
• Check the serial number (S) and identifying pole letter on the
lower insulator flange or on the crankcase flange.
• Check to make sure the serial number agrees with the breaker
serial number.
• Place a wooden board (3) under the rounded area at the bottom
of the pole column. This will protect the pole column during the
erection process.
• Fasten the lifting tackle to the pole column using two M16
eyebolts. Use the two middle holes in the terminal pad mounting
plate for this purpose.
The filling connection (2) of the pole column (1) must face up-
ward during the erection procedure. If the filling connection faces
downward, it could be easily damaged during erection.
CAUTION
1
Pole column
-
2
Filling connection
-
3
Wooden board
Not supplied
3
2
1
S
S
B
A
-P
-A
UF
RI
C
H
T
E
N
Falling loads can result in serious personal injury and damage to
the breaker.
Therefore:
- Never lift the pole columns from the high voltage terminal
pads attached to the pole column. Always use the holes in
the terminal pad mounting plate.
- Do not stand under suspended loads.
WARNING
Summary of Contents for GL 311 F3/4031 P/VE
Page 2: ......
Page 10: ...INTRODUCTION 10 146 OI 250 EN REV7 REV6...
Page 12: ...SAFETY 12 146 OI 250 EN REV7 REV3...
Page 48: ...INSTALLATION 48 146 OI 250 EN REV7 REV7...
Page 80: ...INSPECTION AND MAINTENANCE 80 146 OI 250 EN REV7 REV3...
Page 102: ...RECONDITIONING 102 146 OI 250 EN REV7 REV7...
Page 104: ...END OF LIFE MANAGEMENT 104 146 OI 250 EN REV7 REV2a...
Page 114: ...SPECIAL EQUIPMENT OPTIONAL 114 146 OI 250 EN REV7 REV0...
Page 128: ...REPLACEMENT PARTS AND ACCESSORIES 128 146 OI 250 EN REV7 REV6...
Page 130: ...HANDLING USED SULFUR HEXAFLUORIDE 130 146 OI 250 EN REV7 REV2...