7.6
Functional Testing
7.6.1
Test Operations
• Carry out five closing and five opening operations by remote
control.
7.6.2
Measuring the Running Time of the Charging Motor
After each closing operation, the charging motor automatically re-
charges the closing spring.
• Carry out a closing operation and measure the running time of the
charging motor.
• Compare the running time with the reference values in the routine
test certificate and enter it in the checklist.
Operations at gas pressures below UW2 can result in mechani-
cal damage to the circuit breaker.
Therefore:
- Never operate the circuit breaker at gas pressures below
UW2 (red area on the density monitor indicator).
CAUTION
The pressurized components of the pole columns can be dama-
ged by improper handling. Such damage can cause the pole co-
lumns to burst as the result of breaker vibrations. This can result
in serious personal injury or property damage.
Therefore:
- Always carry out test operations from a protected positi-
on.
WARNING
Long-lasting applied voltage may damage the shunt release
coils.
Therefore:
- Connect coils only by way of the terminals provided.
- Apply voltage to the coils for no longer than three se-
conds.
CAUTION
Summary of Contents for GL 311 F3/4031 P/VE
Page 2: ......
Page 10: ...INTRODUCTION 10 146 OI 250 EN REV7 REV6...
Page 12: ...SAFETY 12 146 OI 250 EN REV7 REV3...
Page 48: ...INSTALLATION 48 146 OI 250 EN REV7 REV7...
Page 80: ...INSPECTION AND MAINTENANCE 80 146 OI 250 EN REV7 REV3...
Page 102: ...RECONDITIONING 102 146 OI 250 EN REV7 REV7...
Page 104: ...END OF LIFE MANAGEMENT 104 146 OI 250 EN REV7 REV2a...
Page 114: ...SPECIAL EQUIPMENT OPTIONAL 114 146 OI 250 EN REV7 REV0...
Page 128: ...REPLACEMENT PARTS AND ACCESSORIES 128 146 OI 250 EN REV7 REV6...
Page 130: ...HANDLING USED SULFUR HEXAFLUORIDE 130 146 OI 250 EN REV7 REV2...