T
ROUBLESHOOTING
OI 250 (EN)
REV7
/REV2
8.2.3
Replacing the Operations Counter
• Detach the operating link (1).
• Remove the operations counter (2) by unscrewing the four M3
mounting screws.
• Set the new operations counter manually to indicate the number
of operations shown on the old operations counter (so that it will
be possible later to determine the life of the breaker).
• Mount the new operations counter.
• Reattach the operating link.
1
Operating link
-
2
Operations counter
-
1
2
Summary of Contents for GL 311 F3/4031 P/VE
Page 2: ......
Page 10: ...INTRODUCTION 10 146 OI 250 EN REV7 REV6...
Page 12: ...SAFETY 12 146 OI 250 EN REV7 REV3...
Page 48: ...INSTALLATION 48 146 OI 250 EN REV7 REV7...
Page 80: ...INSPECTION AND MAINTENANCE 80 146 OI 250 EN REV7 REV3...
Page 102: ...RECONDITIONING 102 146 OI 250 EN REV7 REV7...
Page 104: ...END OF LIFE MANAGEMENT 104 146 OI 250 EN REV7 REV2a...
Page 114: ...SPECIAL EQUIPMENT OPTIONAL 114 146 OI 250 EN REV7 REV0...
Page 128: ...REPLACEMENT PARTS AND ACCESSORIES 128 146 OI 250 EN REV7 REV6...
Page 130: ...HANDLING USED SULFUR HEXAFLUORIDE 130 146 OI 250 EN REV7 REV2...