R
ECONDITIONING
OI 250 (EN)
REV7
/REV7
10.1.12
Adjusting the Double Motion System
• Pull the interrupter unit down until it touches the stop (required
tensile force approx. 200N).
• Align the flattened sides of the connecting rod (31) so that they
are parallel with the high voltage terminal pads (32). Alignment is
accomplished by turning the interrupter unit.
• Adjust the distance between the lower edge of the holder (16) and
the center of the hole in the coupling piece (33) to 69.5±1mm. The
hole in the coupling piece (33) and the flattened sides of the
connecting rod must be aligned in the direction of the high voltage
terminal pads.
• Tighten the nut (34). Tighten to a torque of 130Nm.
Improper adjustment of the interrupter unit can result in damage
during operation.
Therefore:
Carefully adjust and check the following:
- Distance of 69.5±1mm.
- Alignment of the flattened connecting rod side.
- Alignment of the hole in the coupling piece.
CAUTION
31
Connecting rod
1x
32
High voltage terminal pad
1x
33
Coupling piece
1x
34
Hexagon nut, M20x1.5 A2-70
1x
16
34
33
32
69,5±1
31
BA
-P-P
S-
12
Summary of Contents for GL 311 F3/4031 P/VE
Page 2: ......
Page 10: ...INTRODUCTION 10 146 OI 250 EN REV7 REV6...
Page 12: ...SAFETY 12 146 OI 250 EN REV7 REV3...
Page 48: ...INSTALLATION 48 146 OI 250 EN REV7 REV7...
Page 80: ...INSPECTION AND MAINTENANCE 80 146 OI 250 EN REV7 REV3...
Page 102: ...RECONDITIONING 102 146 OI 250 EN REV7 REV7...
Page 104: ...END OF LIFE MANAGEMENT 104 146 OI 250 EN REV7 REV2a...
Page 114: ...SPECIAL EQUIPMENT OPTIONAL 114 146 OI 250 EN REV7 REV0...
Page 128: ...REPLACEMENT PARTS AND ACCESSORIES 128 146 OI 250 EN REV7 REV6...
Page 130: ...HANDLING USED SULFUR HEXAFLUORIDE 130 146 OI 250 EN REV7 REV2...