10
concrete slab
At the appropriate location, construct a concrete slab:
• 28 day compression strength of 3000 psi (200 MPa)
• Minimum 5 inches thick
• Minimum 6 inches wider than enclosure on all sides
(shown as D in figure)
• Strengthen slab with No. 6 reinforcing bars (on
12” centers) or 8 ga. steel wire fabric (6” centers).
note: Avoid placing reinforcement in entrance stub-up
area (shown as (B)).
Attach unit to slab at four corner locations (a) with minimum
5/16” diameter (8mm) masonry anchor bolts long enough to
secure the unit.
The fuel inlet location (c) and the exhaust opening (e) are
shown for reference.
49”
14.25”
94”
78”
44”
9.5”
7”
7.38”
34.25”
10.5”
8”
C
E
D
A
B
electrical and fuel inlet Locations
A through-slab power cable stub-up is preferred (see
figure above). If stub-up’s are not used, (f) indicates the
recommended location for punching holes for attaching
power conduit. The 1 inch N.P.T. fuel inlet connector (c) is
shown for reference.
C
F
Summary of Contents for HOME NERATOR SYSTEM 27000-30000 WATT -