background image

 

7

 

System checks

 

 

Switch ON the Mains (Utility) voltage from the input 
distribution. 
At this stage the electronic power supply is switched ON 
and at the end of a selftest on the display should appear 
“SELF TEST OK” and the buzzer sounds, followed by 
showing the main page. Press “alarm” for reset. 
In case of negative self test, the message “Mainboard 
failure” would appear. Do not proceed with commissioning 
but call the nearest service centre in this case. 
Verify in “User Parameters” for correct Date and Time, if 
necessary adjust. 

 

 

Verification of Parameter settings

 

 

The setting of Parameters allows the programming and 
setting of certain functions and values of the UPS. 
If not otherwise specified, the UPS will leave the factory in 
a standard configuration, which corresponds to the values 
in the attached PIOR. Verify if this values conform to the 
actual situation on site and if necessary adapt. 

 

Important: Keep the PIOR updated whenever Parameter(s) 
are changed !!!! 

 

To access Parameters: 
Go in the “menu” to the page PARAMETER MENU.  
User Parameters can be accessed without Password, since 
these have no influence on the function of the UPS, while 
Service Parameters can be accessed only via Password. 
Password: Change the string XXXXXXXX into YYYYYYYY.  

 

To change Parameters: 

 

Move the cursor with “-“ to the Parameter to change. 

 

Press  “ok” to enter edit mode. 

 

Scroll with “+” and change values with “-“. 

 

Press “ok” to confirm and install new Parameter and 
to exit edit mode. 

 

 

Summary of Contents for Lanpro 33

Page 1: ...tal Energy LanPro 33 Installation and commissioning guide Purpose of this document is to be a guide for the person in charge involved in the installation and the startup of the UPS as a step by step procedure ...

Page 2: ...tic bag containing 3 Battery fuses 6 cable ties for the fastening of input and output cables and 5 Eyelet terminals for the connection of Neutral and Earth cables to the Input Output section of the UPS The description for the installation and startup of the UPS is based on a STANDARD CONFIGURATION i e single UPS with integrated Battery and single Mains Utility input A description of procedures in ...

Page 3: ... Battery 10kVA 500x780x 1280 113kg 247kg 20kVA 500x780x 1280 140kg 372kg 30kVA 660x780x 1280 172kg 520kg Panel remove Frontpanel Pressed on remove with screw driver Sidepanels Fixed wit 3 Allen screws on each side Bottom Panels Front and Rear Pressed on Side Fixed with 2 Allen screws each side ...

Page 4: ...to previous page in metering and alarms or in edit mode change value menu Commands Reset Lamptest Parameters ok Press to execute a command or enter in edit mode to change Parameters Confirm change of Parameter Consult the operating manual for a detailed descriptions of the displayed pages and a listing of alarms and messages and descripton of their particular meaning ...

Page 5: ...utput connection Cable sections European standard Input Output 10kVA 20kVA 30kVA 5 x 4 mm2 5 x 10 mm2 5 x 10 mm2 Use the eyelet terminals from the plastic bag for the connection of Neutrals and Earth to Input Output ...

Page 6: ...5 UPS Frontview with Frontdoor open ...

Page 7: ...e Sidepanes to take them off See page UPS cabinet Before making any connections we recommand a thorough mechanical check including verification of loose bolts or components correct inserted plugs and no loose wires or cables Make sure fans spin freely If any problems with this installation are found that pose a threat to persons or equipment do not proceed until the problem has been corrected Inst...

Page 8: ... of certain functions and values of the UPS If not otherwise specified the UPS will leave the factory in a standard configuration which corresponds to the values in the attached PIOR Verify if this values conform to the actual situation on site and if necessary adapt Important Keep the PIOR updated whenever Parameter s are changed To access Parameters Go in the menu to the page PARAMETER MENU User...

Page 9: ...t Manual Battery test Commands Inverter ON Local Remote Both Input filter Rectifier input voltage Mains filter Bypass voltage Sync filter Alarm not synchronizerd The delay time in seconds installed in one of the above Parameters has effect on the signals from the Panel the events memory and the Customer Interface Programming of the 6 output relays on the Customer Interface Programming of the 2 inp...

Page 10: ...ns voltage 230V Press again simultaneously keys metering and to start the Booster which will bring the DC Voltages up to 400 Volt Verify again in metering for UDCP and UDCN show a correct reading of these voltages Go now in the menu to Inverter ON OFF page and start the Inverter Verify in measurements for correct voltages 220 230 240 Volt Compare with PIOR Press Inverter ON a second time to activa...

Page 11: ...nding of the Buzzer and the blinking yellow LED End of startup in Service mode Shutdown of UPS in Service Mode If everything ok press the button Total OFF to shutdown Booster Inverter and SSM and open the contactors K4 K6 and K7 Before proceeding to normal startup with Q1 closed discharge the Capacitors of the DC Link either by starting the Inverter switch off after discharge or wait until the rea...

Page 12: ...r corresponding values of Mains voltage and Load voltage Close Battery fuses and verify Battery voltage and Battery charging current If possible connect some Load and take note of the amount of Load for each phase Load distribution Yellow LED on frontpanel is lit Choose in menu page Inverter ON OFF and start the Inverter After transfer of the output to Inverter the green LED is lit indicating Load...

Reviews: