Operating Manual
LP 33U Series 30 & 40 kVA
7.1.3 From Manual Bypass Q2 to normal function VFI
This procedure presupposes that the
load
is powered by the
manual bypass
switch, and:
•
The
inverter
is switched OFF;
•
The
manual bypass switch Q2
is closed (Pos. I);
•
The
output switch Q1
is open (Pos. 0);
•
Switch “OFF” battery breaker from Battery Cabinet.
•
LED Alarm
blinks.
NOTE !
This procedure must not be performed if the UPS is used as
frequency converter
.
1. Switch “ON” battery breaker from battery cabinet.
2.
Close the output switch Q1 (Pos. I).
Load
is now supplied parallel through
automatic bypass
and
manual bypass Q2
.
The
synoptic diagram
must display the status
“
LOAD SUPPLIED BY
AUTOMATIC BYPASS AND MANUAL BYPASS Q2
”
.
`
Home\Commands
COMMANDS
RESET TOTAL OFF
REQUEST TOTAL OFF
3.
Only in case it has been previously activated, restore the
command
“Total Off”
by entering the screen:
COMMANDS/
RESET TOTAL OFF
V
`
Home\Meter
BOOSTER
f :
60.0
Hz
L1 :
120
V
L2 :
120
V
L3 :
120
V
Vp :
215
V
Vn :
215
V
4.
Open the manual bypass switch Q2 (Pos. 0).
The
load
is supplied by the
utility
through the
automatic bypass
.
Verify, selecting the screen
METERING/BOOSTER/
Vp
and
Vn
, that the
booster voltage has reached about
215 Vdc
.
5. Insert the inverter by pressing
“
Inverter ON
”
( I ) key.
Some seconds later the
load
will be transferred on
inverter
.
LED Alarm
turn Off and the
LED Operation
must be lit.
The
synoptic diagram
must display the status
“
LOAD SUPPLIED BY
INVERTER
”
.
END OF PROCEDURE