10 INSTALLATION AND MAINTENANCE
10.1 INSTALLATION
10
10 INSTALLATION AND MAINTENANCE 10.1 INSTALLATION
The relay should be installed in a clean, dry and dust-free place, with no vibrations. It should also be well lit to facilitate
inspection and testing.
Operational conditions as defined in section 3 must not be exceeded in any case.
The relay should be mounted on a vertical surface. Figure 3–2:
shows the diagram for panel drilling and mounting.
Given that the design of the MIGII unit is based on high performance digital technology it is not necessary to recalibrate