11 Commissioning Instructions
P50 Agile P253
11-4
P253/EN M/C
2
COMMISSIONING
The P253 is fully numerical in its design. It has a self-supervision function which continuously keeps
track of its internal hardware and will display a message on the LCD screen if it detects the failure of
any component. Therefore, the commissioning tests are less extensive than those for non-numeric
electronic devices or electromechanical relays.
2.1
Commissioning Test Menu
The IED provides several test facilities under the
COMMISSION TEST
menu heading. There are
menu cells that allow you to monitor the status of the opto-inputs, output relay contacts, and user-
programmable LEDs.
This section describes the commissioning tests available in the IED's Commissioning test menu.
2.1.1
Test Mode
The Test Mode menu cell is used to allow secondary injection testing to be performed on the relay
itself without operation of the trip contacts. It also enables a facility to test the output contacts by
applying menu controlled test signals.
To select test mode, the
Test Mode
menu cell should be set to
Test Mode.
This takes the relay out of
service and blocks the maintenance counters. It also causes an alarm condition to be recorded and
the amber
OUT OF SERVICE
LED to illuminate. This action freezes any information stored in the CB
Condition column and in IEC 60870-5-103 builds changes the Cause of Transmission (COT) to Test
Mode.
To enable testing of output contacts the
Test Mode
cell should be set to
Contacts Blocked
. This
blocks the protection from operating the contacts and enables the test pattern and contact test
functions which can be used to manually operate the output contacts.
When testing is complete the cell must be set back to
Disabled
to restore the relay back to service.
2.1.2
Test Pattern
This cell is used to select the output relay contacts that will be tested when the
Contact Test
cell is set
to
Apply Test
.
2.1.3
Contact Test
When the
Apply Test
command in this cell is issued, the contacts set for operation (set to 1) in the
Test Pattern cell change state. After the test has been applied, the command text on the LCD will
change to
No Operation
and the contacts will remain in the Test State until reset issuing the
Remove
Test
command. The command text on the LCD will again revert to
No Operation
after the
Remove
Test
command has been issued.
2.1.4
Test LEDs
When the Apply Test command in this cell is issued, the
4
programmable LEDs will illuminate for
approximately 2 seconds before they extinguish and the command text on the LCD reverts to
No
Operation.
2.1.5
Opto Input Status Check
The
Opto I/P
cell under
SYSTEM DATA
menu can be used to monitor the status of the opto-inputs
while they are sequentially energised with a suitable voltage. The cell is a binary string that displays
the status of the opto-inputs where '1' means energised and '0' means de-energised.
Summary of Contents for P50 Agile P253
Page 3: ...P50 Agile P253 1 Introduction P253 EN M C 1 1 INTRODUCTION CHAPTER 1 ...
Page 4: ...1 Introduction P50 Agile P253 1 2 P253 EN M C ...
Page 11: ...SAFETY INFORMATION CHAPTER 2 ...
Page 12: ...Safety Information Pxxx 2 ...
Page 23: ...P50 Agile P253 3 Hardware Design P253 EN M C 3 1 HARDWARE DESIGN CHAPTER 3 ...
Page 24: ...3 Hardware Design P50 Agile P253253 3 2 P253 EN M C ...
Page 28: ...3 Hardware Design P50 Agile P253253 3 6 P253 EN M C E00276 Figure 2 Hardware design overview ...
Page 32: ...3 Hardware Design P50 Agile P253253 3 10 P253 EN M C ...
Page 33: ...P50 Agile P253 4 Front Panel P253 EN M C 4 1 FRONT PANEL CHAPTER 4 ...
Page 34: ...4 Front Panel P50 Agile P253 4 2 P253 EN M C ...
Page 39: ...P50 Agile P253 4 Front Panel P253 EN M C 4 7 Figure 2 USB port ...
Page 40: ...4 Front Panel P50 Agile P253 4 8 P253 EN M C ...
Page 41: ...P50 Agile P253 5 Configuration P253 EN M C 5 1 CONFIGURATION CHAPTER 5 ...
Page 42: ...5 Configuration P50 Agile P253 5 2 P253 EN M C ...
Page 154: ...5 Configuration P50 Agile P253 5 114 P253 EN M C ...
Page 155: ...P50 Agile P253 6 Protection Functions P253 EN M C 6 1 PROTECTION FUNCTIONS CHAPTER 6 ...
Page 156: ...6 Protection Functions P50 Agile P253 6 2 P253 EN M C ...
Page 182: ...7 Protection Parameter Settings P50 Agile P253 7 2 P253 EN M C ...
Page 203: ...P50 Agile P253 8 Monitoring Control P253 EN M C 8 1 MONITORING CONTROL CHAPTER 8 ...
Page 204: ...8 Monitoring Control P50 Agile P253 8 2 P253 EN M C ...
Page 222: ...8 Monitoring Control P50 Agile P253 8 20 P253 EN M C ...
Page 223: ...P50 Agile P253 9 SCADA Communications P253 EN M C 9 1 SCADA COMMUNICATIONS CHAPTER 9 ...
Page 224: ...9 SCADA Communications P50 Agile P253 9 2 P253 EN M C ...
Page 249: ...P50 Agile P253 10 Installation P253 EN M C 10 1 INSTALLATION CHAPTER 10 ...
Page 250: ...10 Installation P50 Agile P253 10 2 P253 EN M C ...
Page 260: ...11 Commissioning Instructions P50 Agile P253 11 2 P253 EN M C ...
Page 270: ...11 Commissioning Instructions P50 Agile P253 11 12 P253 EN M C ...
Page 272: ...12 Maintenance and Troubleshooting P50 Agile P253 12 2 P253 EN M C ...
Page 282: ...13 Technical Specifications P50 Agile P253 13 2 P253 EN M C ...
Page 292: ...13 Technical Specifications P50 Agile P253 13 12 P253 EN M C ...
Page 293: ...P50 Agile P253 14 Wiring Diagrams P253 EN M C 14 1 WIRING DIAGRAMS CHAPTER 14 ...
Page 294: ...14 Wiring Diagrams P50 Agile P253 14 2 P253 EN M C ...
Page 297: ......