background image

              

 

 

Nuova Via di Piano Comprensorio Vulcano 

Sesto San Giovanni, MI 20099 Italy 

Tel. 02-24105.001 

 

IS 2653 GB

 

Page 

4

 of 

18

 

 

 
Main safety risks related to the bushing handling and its operative conditions are: 
 

  Transport and handling of heavy and large parts. 

  Lifting and moving of heavy and not well balanced components. 

  Work operations under the crane and suspended materials. 

  Work at height. All operation at height

 

must be performed on a suitable certified platform. 

  Risk of falling down of heavy parts during the installation. 

  Risks deriving from un-proper balancing of the masses that can cause un-expected rotation during the 

installation on the wall. 

 

Risks due to the use of un-proper tools or wrong operations.

 

  Risks  deriving  from  un-proper  installation  or  operation  on  the  bushing  when  filled  by  SF6  gas  at  rated 

filling pressure (explosion). 

  Environmental risks related to dispersion of SF6 gas in the atmosphere. 

  Severe electrical shock risk related to the extremely high voltage AC/DC level of the equipment. 

  Severe electrical shock risk due to un-proper realization of the bushing grounding connections. 

  Severe electrical shock risks deriving by the fact that the composite insulator and the other main parts of 

the bushing could remain electrically charged at high voltage for a long period of time after the plant de-
energizing and the bushing grounding. Before starting any work on the de-energized bushing, check the 
discharge  by  touching  all  surface  of  both  indoor  and  outdoor  side  composite  insulators  and  all  other 
parts of the bushing with an insulated grounding rod which length must be 

 3m. Operators must wear 

protective insulating gloves and boots and helmet with protective transparent face shield. 

 
2.1 

Preliminary operative information 

 

The  following  notes  are  mandatory  for  personnel  involved  in  wall  bushing  assembly.  All  problems  detected 
during the bushing installation must be reported to the Foreman and to GE Grid Solutions RPV Supervisor. 

 

  The  bushing  is  a  pressurized  device.  Operations  on  the  valves,  pressure  gauges,  pipes,  protective 

devices  must  be  performed  by  qualified  operators,  with  the  proper  equipment  and  respecting  the 
instructions of this manual. Foreman and operators have to take careful for handling the pressurized 
equipment. 

  It is mandatory to use clean safety gloves and protective clothes, helmets and safety shoes during all 

bushing moving, assembly, hauling and installation operations. 

  Work in quote will be done by trained operators on adequate and certified moving platforms. Workers 

that will operate in quote must use the above prescribed safety devices and in addition they must wear 
certified safety harnesses. 

  Lifting equipment must be adequate and certified. 

  Tools and pieces of clothes or no-fibre fabric used during the installation must be clean. 

  The composite insulators sheds are made by silicone that can be mechanically damaged if not properly 

handled.  Protect  the  insulators  with  clean  plastic  foils  during  the  bushing  installation  and  report  to 
Foreman and to GE Grid Solutions RPV Supervisor any event which could have caused a damage of 
the composite insulators.

 

 

CAUTION:

 It is strictly forbidden to move, lift and install any equipment that is under pressure. Check through 

appropriate gauge that the devices are at a pressure less than or equal 0.15 MPa abs (0.5 bar gauge) before 
operate on them. 
 

CAUTION:

  The  bushing  is  equipped  with  a  safety  rupture  disk.  This  is  installed  on  the  central  flange  and 

protected by a metallic cap. Do not remove this protective cap and its relevant mechanical parts. Never touch 
the safety disk with the bushing filled with gas, as it can break, causing a violent gas explosion. Maintenance 
operation on the safety disk is allowed to trained operators and only after removing all gas pressure. 

Summary of Contents for PWHS

Page 1: ...pany name udated 07 07 2016 AF LP 3 Storage and transport conditions updated 22 08 2016 AF LP IS 2653 GB GE Proprietary Information Class III Confidential Export Controlled U S Government approval is required prior to export from the U S re export from a third country or release to a foreign national wherever located GAS FILLED HV WALL BUSHING PWS PWHS OPERATING AND MAINTENANCE INSTRUCTIONS ...

Page 2: ...3 3 Storage conditions 6 4 Technical characteristics 6 5 Bushing preparation and installation 7 5 1 Controls at the arrival 7 5 2 Bushing unpacking 8 6 Gas SF6 characteristics and gas filling instruction 10 6 1 Gas first filling operation and control of alarm and tripping signals 11 6 2 Gas refilling during the bushing normal operation 11 7 Gas density monitor 13 8 Power factor taps 14 9 Composite...

Page 3: ...voltages above 1000V 2 Safety In this document important safety requirements are highlighted by the word CAUTION and important operative instructions are evidenced by the word NOTE This manual must be available to the personnel responsible of the installation operation and maintenance of the bushings The wall bushing is a high voltage AC DC device filled under pressure with SF6 gas that has to be ...

Page 4: ...personnel involved in wall bushing assembly All problems detected during the bushing installation must be reported to the Foreman and to GE Grid Solutions RPV Supervisor The bushing is a pressurized device Operations on the valves pressure gauges pipes protective devices must be performed by qualified operators with the proper equipment and respecting the instructions of this manual Foreman and op...

Page 5: ...ent of the crate during the transport it is responsibility of the transport company to carefully fix it on the vehicle by suitable retain systems like ropes synthetic pulling bands or any other method The maximum allowed transport acceleration along the three axis is 3g 29 43 m s2 In case of transport by truck along very bad roads bumpy roads the speed must be adequately reduced to max 30 km h Tru...

Page 6: ...ned and tested in accordance with the IEC 62199 and IEC 60137 standard Each section is based on A composite insulator with silicone sheds The internal shielding arrangement An internal aluminium tube conductor The top flange with the line terminal The top toroidal electrical shield The two sections joined by the central flange make the complete bushing The sealing joints between the parts are desi...

Page 7: ...t the arrival Before proceeding with the unpacking operation it is necessary to perform the following controls Check the wooden crate status Check the external visual impact recorder s Open the crate and inspect packaging and goods inside see next paragraph 5 2 Check the pressure of the gas inside the bushing that must be 0 11 MPa abs 0 1 bar gauge see Figure 3 Check the composite insulators statu...

Page 8: ...supports and it is locked by locking belts Additional intermediate belts support the composite insulator to a wooden structure Figure 4 Bushing crate inside view Figure 5 Bushing inside the crate top view The transport box can be lifted by a suitable crane After the opening of the crate the visual inspection of the bushing and the removal of the locking ropes and locking blocks the bushing can be ...

Page 9: ...low the steps indicated into the provided erection and installation manual IS 2654 GB Figure 7 Example of bushing extraction and lifting CAUTION The two composite insulators are protected by a PE plastic foils Remove the protection only after the installation of the bushing on the wall and just before the energizing CAUTION To lift the bushing do not wrap ropes i e tie lifting method around the si...

Page 10: ...mium Supplier The minimum requirement is that the characteristics will be in accordance with the data listed in the GE RPV limits column The gas filling must be performed with an equipment that prevents dispersion of the SF6 gas in the atmosphere As an example next Figure 8 shows a gas plant manufactured by the German company DILO GmbH Figure 8 Vacuum filling gas plant DILO and connecting valves N...

Page 11: ...re up to 0 2 MPa abs 1 bar gauge Pressure must be directly measured on the gas density monitors installed on the bushing flange Check all the gas seals for leakages with a suitable SF6 leak meter device In case of significant leakages stop activities and contact GE Grid Solutions RPV supervisor If the bushing does not show any leakage gradually increase the pressure at the rated filling pressure v...

Page 12: ... the DILO machine check that the machine set up is for gas filling and that the connecting pipe is full of SF6 In the case of direct filling from the bottle check that the bottle is effectively charged with SF6 that the gas quantity is sufficient for the re filling the pressure reduction unit and the pipe are compatible with the DILO filling system and all equipment is specific for SF6 filling app...

Page 13: ...cation on the scale is expressed in MPa absolute referred to a gas temperature of 20 C This means that the instrument converts the gas density into a value of pressure referred to 20 C independently for the effective temperature of the gas The instrument reading practically does not change with the gas temperature that is a function of the bushing loading condition and ambient temperature Changing...

Page 14: ...epair procedure is described into the component manual see reference in the summary prepared for the specific wall bushing The composite manufacturer can provide a repairing kit and also a technical support for the repairing activity Useful indications about the composite insulator maintenance plan main actions are shown in Table 2 CAUTION Severe electrical shock risks deriving by the fact that th...

Page 15: ... the camera must be properly set in order to avoid false signals and background noise In addition an infrared scan on the line terminal and the incoming cables can reveal incipient hot spots phenomenon that can evolve into a serious damage on the electrical connection and then of the bushing itself In case of significant variation of the UV and IR emission plan the following actions UV emission Im...

Page 16: ... Gas valves electrical equipment and connecting cables When plant is off Clean the cubicle Check for gas leaks Check functionality of pressure gauge and DILO Type valves Check terminal blocks wiring cables and cable glands Check and clean the junction box Check all gas joints to the DILO Type valves on the bushing Check the cables and the cable tray to the bushing Current terminals When plant is o...

Page 17: ...pect the closure cap and the fixing screws CAUTION Do not remove the closure cap and do not touch the disk when the bushing is filled with gas An explosion of the disk could be very dangerous Gas density monitor 5 years Check calibration and operation of micro switches Check the effective and correct operation of the alarms tripping signal chain from the instruments to the substation systems Bushi...

Page 18: ...electric terminals Copper silvered Dismount and recycle Toroids Aluminium Dismount and recycle Internal electrostatic shields Aluminium Dismount and recycle Transport supports Aluminium Recycle the aluminium Teflon Dispose or thermo destruction Composite insulators with flanges Fibreglass Dispose or thermo destruction Silicone Dispose or thermo destruction Aluminium Dismount and recycle Electrical...

Reviews: