GE Healthcare
Senographe DS
Revision 1
Service Information and Procedures Class A 2385072-16-8EN
Job Card D/R A331 - UPS
Page no. 1521
Chapter 9
JC-DR-A-331.fm
Job Card D/R A331 - UPS
Chapter 9
1
SUPPLIES
2
TOOLS
3
REQUIRED EFFORT
Personnel: 1 Field Engineer
Time: 30 minutes
4
SAFETY PRECAUTIONS
WARNING
Before beginning work, shut down the equipment correctly and switch off the Senographe
system hospital supply circuit breaker. Lock it in the off position or mark it clearly with a
warning sign to prevent others from applying power
.
5
PREREQUISITES
Remove the Control Station Omega cover. See
Job Card PHY A040 - Remove/Reinstall Control Station
6
PROCEDURE ON V1/V2 CONTROL STATIONS
6-1
Disassembly of the UPS on V1/V2 Control Stations
1. Locate the UPS unit (1) inside the Control Station.
2. Disconnect all cables from the UPS unit rear panel.
1