Scenario PHY A001 - Physical Installation
Chapter 6
1
CONTEXT
This Scenario provides information for the physical phase of a first installation of Senographe equipment
on the customer site.
The installation is split into two phases:
•
Physical installation: positioning and cabling the various sub-systems without applying power. This is
treated in this scenario.
•
Electrical installation: powering on the system, configuration, and verification, up to start-up with the
customer. Refer to chapter
2
STEERING GUIDE
Refer to the following Steering Guide for an outline of the recommended sequence of physical installa-
tion.
Physical Installation Steering Guide - Preparation, Physical Installation, and Connection.
Step
Job Card
Comments Done
Preparation
1
Schedule appointments: Delivery date,
movers, etc.
None
2
Check room preparation (See PIM inspec-
tion report and the structural engineer site
survey report)
None
Physical Installation
3
Unpack Generator and Gantry pallet
Move Gen Gantry to X-ray room
Job Card PHY A001 - Unpacking the
Two
persons
required
4
If the hospital doors are too low for the
height of the Gantry with its covers on,
remove the Gantry Covers
Job Card PHY A044 - Remove/Rein-
.
5
If the hospital site does not allow you to
transport the Generator and Gantry
together, disconnect them and move them
individually into the X-ray room
Generator Disconnection Procedure
in
Generator and Gantry Disconnection
6
Unpack Control Station
Move Control Station to X-ray room
Job Card PHY A002 - Unpacking the
Two
persons
required
7
Establish the optimum positions for Gan-
try, Generator, and Control Station and
decide whether the LCD Monitor must be
mounted on the other side.
Obtain the customer agreement.
Anchor the Gantry and the Control Station