Modifications reserved
Page 11/49
OPM_SGS_ISG_M75_M75_2US_V010.doc
Installation Guide
SG Series 750 UL S2
&
SG Series 750 T12 UL S2
3
INSTALLATION
3.1
TRANSPORT
The two cabinets of the UPS are packaged on a pallet suitable for handling with a forklift.
Pay attention to the
center of gravity
.
The cabinets must be moved in
upright position
.
Do not tilt cabinets
more than +/- 10°
during handling.
Move each cabinet in it’s original package to the final destination site.
Do not stack other packages on top: This could damage the UPS
.
If the UPS cabinets must be lifted by crane, use suitable lifting straps and spreader bars.
Note of the center of gravity (for rectifier and inverter cabinet) marked on the package.
Forklift
The UPS may be lifted with a forklift in
upright position.
Take note of the
CENTER OF GRAVITY
marked on the package.
Forklift
=
=
Centre of Gravity
=
=
Centre of Gravity
Fig. 3.1-1 Position of the forklift when moving the unpacked rectifier cabinet
WARNING !
Check for sufficient floor and
elevator loading capacity.
Transport UPS only in upright
position.
Do not stack other package on
top of the UPS.
=
=
Centre of Gravity
=
=
Centre of Gravity
Fig. 3.1-2 Position of the forklift when moving the unpacked inverter cabinet
WARNING !
When loading / unloading and when
moving the UPS, it is forbidden:
When loading / unloading and when
moving the UPS, pay attention to:
Center of Gravity
Center of Gravity