ES-699 Rev U
Page 2 of 17
2
GENERAL REQUIREMENTS
Installation and maintenance must be performed only by qualified personnel.
Area Classification, Protection Type, Temperature Class, Gas Group, and
Ingress protection must conform to the data indicated on the label.
Wiring and conduit must conform to all local and national codes governing the
installation. Wiring must be rated for at least 5ºC above the highest expected
ambient temperature.
Approved wire seals against ingress of water and dust are required and the NPT
fittings must be sealed with tape or thread sealant in order to meet the highest
level of ingress protection.
Where the protection type depends on wiring glands, the glands must be certified
for the type of protection required.
The metal housing is a die-casting alloy which is predominately aluminum.
Before powering the SVI-II AP:
Verify that the pneumatic and electronic cover screws are tightened. This
is important to maintain the ingress protection level and the integrity of the
flameproof enclosure.
If the Installation is Intrinsically safe, then check that the proper barriers
are installed and the field wiring meets local and national codes for an IS
installation. Never install a device, which was previously installed without
an intrinsically safe barrier, in an intrinsically safe system.
If the pneumatic system is powered by a combustible gas then the
installation must be treated as Zone 0 or DIV I.
If the Installation is Non-Incendive, then check that all the electrical
connections are made to approved devices and wiring meets local and
national codes.
Verify that the markings on the label are consistent with the application.
Verify that the air supply pressure can not exceed the marking on the
respective
label.
!WARNING!
Failure to adhere to the requirements
listed in this manual may cause loss
of life and property.
74
GE Oil & Gas
ValVue SVI II AP Quick Start
Summary of Contents for SVI II AP-2
Page 6: ...GE Oil Gas SVI II AP Quick Start Guide 6 ...
Page 10: ...10 GE Oil Gas ValVue SVI II AP Quick Start This page intentionally left blank ...
Page 64: ...64 GE Oil Gas ValVue SVI II AP Quick Start This page intentionally left blank ...
Page 90: ...90 GE Oil Gas ValVue SVI II AP Quick Start Spare Parts ...
Page 91: ...91 Specifications and Spare Parts ...