35
Contractor’s manual
F15 - F30 Generators
Manual For F15 and F30 - Mill.: 2008 - 11 / Mod. : JPM 05
Page
Commissioning Check List
2. After turning the power on:
Manually activate the torque limiter then rearm it
(red lever),
(according to instructions) (complete standstill of the generator and generating set unit)
Check the direction of rotation of the reducer
(refer to the arrow painted on the upper part – clockwise)
Check the working order and the adjustment of the dosing pump
(where relevant)
Set the "work" timer to between 0 and 15 s if the machine is connected to a power station,
then set the reducer motor timer to 180 s.
Preload the refrigerating circuit after vacuumizing
3. After commissioning:
After having turned on the liquid solenoid valve, time the filling time of the
cylinder
(see suction outlet icing)
(connection to central system)
Transfer this time to the “working” time delay
(adjust value if need be)
The commissioning of the reducer and pump after time delay
Adjusting the evaporating pressure reducer
(where relevant)
(in order to obtain the pressure recommended by GENEGLACE at the time of the order)
Set the expansion valve to 6/8K by reference to the bulb
(temperature at the bulb minus the temperature of evaporation at the generator)
Adjusting the wipers
(according to instructions)
The level of water in the upper basin and that of the water tray base
(according to instructions)
The oil level at compressor indicator
(to be monitored also later)
4. After 10 - 15 minutes’ operation, check:
The level of water in the base
(according to instructions)
(that no water drains out of the overflow tube)
Removal of the ice without the reducer motor gear moving
Spraying of water droplets on the strip of the salt measuring device
(where relevant)
The drip of the dosing pump
(where relevant)
The feedback of the oil level to the compressor indicator
(according to the type of installation, extra oil
may be required)
The operating pressures
(according to defined production)
Stop the generator with the I.L.D (check if installed), then the Stop button., check the level of water
in the water tray base
(according to instructions)
(check to make sure that no water drains out of the overflow)
Re-commission the installation and fill in the operation report sheet