7
Start-up
7.1
Safety notes
Initial commissioning
For initial commissioning, the following principles apply:
•
Take protective measures against dangerous contact voltages in accordance
with pertinent regulations.
•
The control top must be completely assembled and correctly adjusted. All
screw connections must be securely tightened. All electrical cables must be
installed correctly.
•
Reliably secure machine parts which have already been connected against
inadvertently being switched on.
•
After conversion of the control top, residual risks must be reassessed.
Hint!
The optional external sensor in the lantern is still in the original
factory setting and must therefore be reset during initial
commissioning, see Section 7.2, Page 67. The manufacturer will not
accept any liability for malfunctions. The risk is borne solely by the
operating company.
Commissioning
For commissioning, the following principles apply:
•
Only allow properly qualified staff to set the control top into operation.
•
Make sure all connections are properly established.
•
The safety devices for the control top must be complete, fully functional and in
perfect condition. Check the function before starting any work.
•
When the control top is switched on, the danger zones must be free.
•
Remove any liquids that have escaped without leaving residues.
7.2
Commissioning – Control Top without Solenoid Valves
Activating the Control Top
Once the control top has been properly mounted on the valve and the electrical
connections have been established correctly, commissioning can be carried out.
Requirement:
•
The process valve must be in the safety position, i.e. an external solenoid
valve must not be actuated.
Carry out the following steps:
1.
Check the function of the external solenoid valve.
2.
Switch on the power supply.
3.
Press the relevant buttons to switch to programming mode, see .