DELIVERY
Receiving the delivery
The following matters should be checked when receiving the district heating substation delivery:
There are no signs of damage during shipping
The delivery corresponds to the order in all aspects
After verifying that the product is in good condition and corresponds to the order, sign the waybill
and keep your copy stored
If the delivery has been damaged during shipping, fill in the shipping damage form immediately.
The form must be signed by both the recipient and the forwarder’s representative (such as the driver). Each driver carries
the form for reporting shipping damage.
Moving the substation
The district heating substation is mounted on a transport platform that allows the substation to be moved and lifted to the site of
installation by means of a pallet jack and lifting slings. Plan the easiest route to the site and be careful not to break floor and wall
surfaces, stairs, door frames or other structures on the property.
Do not damage the substation during lifting! The district heating substation contains fragile components. If the delivery includes
separate lifting instructions or designated lifting points, these must be followed carefully. The heat distribution substation may not
be lifted without the support of the transport platform. The transport platform under the district heating substation may not be
removed until at the site of installation.
Storage
If the district heating substation is stored before installation, ensure that the site of storage is warm and dry.
INSTALLATION AND COMMISSIONING
Installation
The district heating substation may be installed and connected only by a professional technician. The connections must comply with
local standards and regulations.
Move the district heating substation to the site of installation according to the instructions under section “Moving the substation”.
Sufficient space must be reserved around the substation for installation and maintenance. The substation is installed directly on the
floor and does not need to be mounted on the platform.
Use the adjustable legs included in the delivery to adjust the substation at the desired height. The district heating substation should
be level. Tighten the tension nuts on the adjustable legs carefully to ensure that the substation remains level and in the correct
position.
Inspect and tighten all joints in the district heating substation as they may have loosened during shipping.
Check that the product corresponds to the plans and technical specifications included in the separate delivery materials.
All aids used during transport must be removed before commissioning the district heating substation.
Before installation, all pipes and couplings must be cleaned and rinsed.
Pipe connections
Ensure that all pipe connections are in accordance with the plans and technical specifications included in the delivery materials.
Threaded, flanged and welded couplings are used for connecting the substation to the district heating network and internal
networks.