MEASURES DURING OPERATION 

 

Servicing 

 

Monitoring and regular maintenance are important for ensuring that the district heating substation is kept in good working order. 
 
Use a professional maintenance provider when your equipment needs to be serviced. 
 
Service inspections must be performed at least twice per year, before and after the heating season. 
Comprehensive preventive maintenance by a maintenance provider should be performed yearly. 
 
Flow mediums that differ from the technical specification may not be used in the heat exchanger. By default, the medium is water 
without a corrosive agent. 
 
In matters related to warranty, contact Gebwell Oy maintenance services. The warranty terms are included in the delivery materials. 
 

Cleaning heat exchangers 

 

Under normal conditions, the heat exchangers do not need to be cleaned. The powerful turbulent flow creates a continuous self-
cleansing effect on the heat delivery surfaces. If the heat exchanger becomes dirty for any reason, it can be cleaned by backflushing 
and, if necessary, a suitable detergent solution. 
 

Checklist, general points to monitor 

 

Check at least the following before and after the heating season: 
 

 

Possible leaks 

 

Secondary side pressure should be in line with plans 

 

No extraordinary sounds during operation 
 

Checklist, annual preventive maintenance by a maintenance provider 

 

 

Clean the sanitary trap if necessary 

 

Input and output temperatures must be in line with plans. 

 

Control device tuning 

 

Pressure losses in the heat exchangers 

 

Water heat loss must be in line with the requirements of the local district heating provider. 

 

Initial pressure of the expansion tank 

 

Inspecting the pump’s operating point 

 

Regulator tuning orders 

 

Tuning for the Ouman regulator is ordered from Ouman Oy, tel. +358 424 8401.  
Tuning of other regulators can be requested from Gebwell Oy, tel. +358 400 897 492 / Olli Koponen. 

 

 

Summary of Contents for G-Power

Page 1: ...Installation Operation and Maintenance Manual G Power District Heating Substation...

Page 2: ...gy and the environment Optimal savings are achieved through combined heat and electricity production which has a fuel efficiency of 80 to 90 DISTRICT COOLING IN GENERAL District cooling is an environm...

Page 3: ...mperature and pressure warning Check the maximum pressure and temperature values for the equipment from the machine plate Compare these values to those given by the district heating supplier The distr...

Page 4: ...tion Storage If the district heating substation is stored before installation ensure that the site of storage is warm and dry INSTALLATION AND COMMISSIONING Installation The district heating substatio...

Page 5: ...rainage valves are closed Surge tank is connected Threaded and flanged couplings are tightened Safety valves are inspected and operational Fill the district heating substation with the flow medium and...

Page 6: ...d The powerful turbulent flow creates a continuous self cleansing effect on the heat delivery surfaces If the heat exchanger becomes dirty for any reason it can be cleaned by backflushing and if neces...

Page 7: ...exceeding the permitted maximum pressure pressure shocks external strain temperature mechanical strain etc repairs by a maintenance company other than one approved by Gebwell Oy poor quality of circul...

Page 8: ...Gebwell Ltd Patruunapolku 5 FI 79100 Lepp virta FINLAND Business ID 2008956 7 Tel 358 0 20 123 0800 Telefax 358 0 17 554 1102 info gebwell fi www gebwell com...

Reviews: