12.4.5  Operating modes of BLC 100

Warning! Turn on the unit, keeping both on-off switches in the „OFF“ position. After turning on,
wait the end of built-in control BLC (about 10 s). After the light-emitting diode „Netzbetrieb“
(Work from the circuit) has lighted up, a desired operating mode can be chosen by the on-off
switches.

Start of the electric plant in the presence of load

In this operating mode, the electric plant starts immediately with closed
contacts X1.6 and X1.7. After the electric plant is warmed up, load is
connected.

When the switch is turned to the AUS position, the generator is
immediately disconnected.

After 30 s, the engine stops. If contacts X1.6 and X1.7 are not closed,
the electric plant does not start. After the closure of contacts X1.6 and
X1.7, the electric plant starts immediately. After warming up, it accept
load. After the direct-mode switch is opened, the electric plant is imme-
diately disconnected. If contacts X1.6 and X1.7 are opened again, the
generator is disconnected after 5 s.
After 30 s, the engine is turned off

The control of the voltage of a circuit with automatic start

The ATS/Control mode of the circuit is turned on. Light-emitting diode „ATS-
Betrieb“ (ATS mode) blinks. The electric plant is turned on with a delay of 4
s after the disappearance of circuit voltage.

Start of the electric plant in the absence of load and with the control
of circuit voltage

In this mode, the electric plant starts immediately, in the absence of load
(hot-reserve mode). Circuit voltage is monitored, and when it disappears,
the generator contactor connects a consumer to the electric plant after 2 s.
After the direct-mode switch is opened, the electric plant is immediately tur-
ned off.

OFF.

Circuit voltage is not monitored, the electric plant does not start. Warning!
If both switches are in the „OFF“ position, all messages on faults are erased

12.5  Protective circuit breaker (option)

The protective circuit breaker is a switch with an electromagnetic breaker, which is automatically opened when leakage current exceeding rated breaker-triggering current flows on the ground or through the
case. The application of the protective circuit breaker is an additional safety measure against a direct touch. This device is intended to prevent the appearance of both dangerous voltage on open current-
carrying parts of electrical devices and fires. Warning! Before the connection of the electric plant, it is necessary to check its serviceability by the test button of the protective circuit breaker. If the circuit
breaker is not triggered, it is forbidden to use the electric plant. See electrical connection schemes 100118 and 100119.

12.6  Control of insulation resistance in agreement with GW 308 (option)

The control of insulation resistance in combination with the standard protective measure «protective separation» is an additional protective measure in an IT circuit. Since the first short circuit on the case or
defect of insulation is not destructive and consequently remains unnoticed, the insulation control device, which reveals such defects and disconnects consumers, is useful and recommended by GW 308. The
neutral wire (N) and potential-equalization wire (PE) should not be connected with each other. The potential-equalization wire should be connected without breaks between the electric plant and all consu-
mers. The plant can be used without grounding. Before each connection, it is necessary to check the serviceability of the insulation control device by pressing the test button. In this case, a red control lamp
must light up, and the main switch must be opened. The red control lamp „ISO-Fehler“ (Insulation fault) is constantly on before opening the main switch when the insulation of the generator, as well as the
insulation of the consumer, is defective. See electric connection schemes 100110 and 100111.

12.7. 

Measuring instrument for insulation resistance (A-Isometer) (option)

The insulation resistance control in combination with the standard protective measure «protective separation» is an additional protection measure in an IT circuit. Since the first short circuit on the case or
defect of insulation is not destructive and consequently remain unnoticed, the insulation control device, which reveals such defects and disconnects the circuit, is a useful device with a light indicator accor-
ding to VDE 0100-410. The neutral wire (N) and potential-equalization wire (PE) should not be connected with each other. The potential-equalization wire should be connected without breaks between the
electric plant and all consumers. The plant can be used without grounding. Before each connection, it is necessary to check the serviceability of the insulation control device by pressing the test button. In
this case, a red control lamp must light up. The red control lamp „ISO-Fehler“ (Insulation fault) is constantly on before breaking the supply circuit when the insulation of the generator, as well as the insulation
of the consumer or wiring, is defective. See electric connection schemes 100114 and 100116.

Summary of Contents for 4401 E -AA/HEBA

Page 1: ...fax 49 7267 806100 www metallwarenfabrik com 4401 E AA HHBA 4401 E AA HEBA 5401 ED AA HHBA 5401 ED AA HEBA 6401 ED AA HHBA 6401 ED AA HEBA 7401 ED AA HHBA 7401 ED AA HEBA 7401 E AA HHBA 7401 E AA HEBA...

Page 2: ...2...

Page 3: ...Fuel cock Sockets Silent economic fast start switch Starting handle Ignition key switch Drain plug Oil filler neck Oil level indicator Filler neck of the fuel tank Ground screw Air filter Silencer Fu...

Page 4: ...y On the contrary electric power is often necessary urgently by inquiry similarly to the circuits of power supplying enterprises By using the Geko Silent Economic mode the rotation frequency of the en...

Page 5: ...ric test requirements to waste gases in the world accep ted in California California Air Resources Board for 2006 Automatic stop at low oil level OHV reduces the consumption of oil by 50 reduces the c...

Page 6: ...required short circuit current of the generator is insufficient for the circuit breaker of an available consumer or the wire resistance is more than 1 5 M it is necessary to provide protection measur...

Page 7: ...dicator 2 Insert the oil level indicator into the filler neck but do not screw 3 If the oil level is low it is recommended to add oil up to the edge of the filler neck It is necessary to use oil for f...

Page 8: ...the fuel cock to the ON position 2 If necessary close the air valve At hot start the valve opens automatically Warning Do not use the valve if the engine is hot or the tempera ture of air is high Fue...

Page 9: ...Warning When the cord retracts back do not release the handle It should be moved accurately in order to pre vent the damage of the starting device Electric start all types For the start by the electri...

Page 10: ...FFS 100 for remote start and stop of the electric plant option The device is made in the form of a compact module Geko SMD Due to the small sizes of the transmitter a user can constantly carry it wit...

Page 11: ...r sig nals are processed by a microprocessor The parameter is chosen by arrow keys Change of the parameters of maintenance periodicity the calibrations of voltage and current and the reset of the oper...

Page 12: ...he first maintenance i e after this time the first maintenance must be car ried out 2 500h Operating time remaining to the second maintenance i e after this time the second maintenance must be carried...

Page 13: ...ules and other instructions of the manufacturer should be executed every time when working with this device If you have no instructions on work with the equipment appeal to a representative of the man...

Page 14: ...s lead to danger to life the possibility of heavy physical injuries or material damage Attention If a BLC equipped genset will be started with disconnected battery or reverse connected battery a 2A fu...

Page 15: ...ion of the electric plant with BLC 100 See electric schemes 100107 100108 and 100132 The circuit is connected to a head on the face panel of the distribution box Output voltage is taken through a CEE...

Page 16: ...t it is necessary to check its serviceability by the test button of the protective circuit breaker If the circuit breaker is not triggered it is forbidden to use the electric plant See electrical conn...

Page 17: ...tional The additional fuel tank enable extra long running times of the genset A mechanical engine driven pump deliver the fuel from the lower tank to the careburator The standard 20l tank remain usabl...

Page 18: ...turn short circuit in stator replace the stator by a new one Overcurrent circuit breaker Actuate or replace the circuit is actuated or defect breaker Insufficient rotation speed run up to rated speed...

Page 19: ...the authorized workshops in the Appendix Mount only original components when replacing them 14 Scheduled maintenance Before the beginning of maintenance works the engine should be stopped 14 1 Electr...

Page 20: ...Remove the ignition wire from the spark plug Unscrew the spark plug by a spark plug wrench If necessary clean electrodes by a brass brush If the spark plug is damaged replace it Check the interelectro...

Page 21: ...lywheel again turn the central nut Unscrew four screws with six sided heads drawing moment 7 3 N m and remove the fan case Weaken the clamp and remove the fan propeller Unscrew screws and remove the b...

Reviews: