Commissioning and Setup

34

Installation Manual for Generac PWRCell Inverter

send commands to REbus-powered devices. In this way,

a PWRcell inverter behaves like a master device. If two

or more master devices are communicating on the same

PLM channel, REbus devices become unable to respond

properly  to  the  intended  master  device  and  the  master

devices will attempt to provide control for the other, often

leading  to  communication  and  reporting  issues. This  is

referred to as cross-talk.

How to identify PLM Crosstalk

Cross-talk  can  be  easily  identified  by  navigating  to  the

device pages on an inverter control panel. If two inverter

device  pages  exist,  crosstalk  has  occurred.  Similarly,  if

any  REbus  devices  from  one  inverter  show  up  on

another, crosstalk has occurred.

NOTE: 

To  differentiate  one  inverter  device  page  from

another, confirm the RCP numbers via the device page

sub-menu.

NOTE: 

It is recommended to keep a list of which REbus

devices are connected to specific inverters at multi-sys

-

tem sites. 

Multiple Inverter System Pre-Commissioning 

Checklist

Before commissioning multiple inverter systems, confirm

the following:

Inverter systems (including PV Links and PWRcell

batteries)  have  been  installed  per  manufacturer

instructions  and  to  local  and  state  code  require

-

ments.

PWRcell  batteries  have  their  Battery  Disconnect

switches in the OFF position.

PWRcell  inverters  are  de-energized  with  no  volt

-

age present at their AC Grid input terminals. Use

an appropriately rated multi-meter/voltmeter to ver

-

ify if AC voltage is present at the AC Grid terminals.

NOTE: 

To  determine  if  the  inverter  is  de-energized,

check the inverter control panel and the system backfeed

breaker. If de-energized, the inverter control panel will be

powered  off  and  the  inverter  backfeed  breaker  will  be

OPEN.

Multiple Inverter System Commissioning 

Procedure

NOTE: 

Throughout this process, it is important that only

one  inverter  is  energized  at  any  time.  If  two  or  more

inverters are energized at any point during this process,

the  inverters  will  cross-talk.  To  resolve  crosstalk,  see

PLM  Crosstalk  Recovery  Procedure

.  After  resolving

crosstalk,  the  commissioning  process  will  need  to  be

restarted for the cross-talked inverters.

1.

Close  the  AC  backfeed  breaker  to  supply  AC

power to one PWRcell Inverter AC Grid Input/Out

-

put Terminals. This will allow the inverter to ener

-

gize and illuminate the Inverter control panel. 

2.

Perform 

Commissioning the System

 steps 1-7.

3.

Modify the PWRcell inverter PLM Channel to 0.

NOTE: 

PLM Channel 0 is a catchall channel. Only use

for  inverters  during  programming.  Do  not  set  REbus

devices to channel 0. Do not leave inverter on channel 0. 

4.

Choose a channel from 2 – 12 to use as the only

number for addressing all devices on the system.

The goal is to address the system to its own unique

channel across all devices.

NOTE: 

Do not leave any device, including the inverter,

on channel 0 or channel 1 by the end of the process.

5.

Use  arrow keys to navigate to all REbus  devices

(expect REbus Beacon) to change the PLM chan

-

nel.

6.

Access Mod. Settings for each device and change

the PLM channel to the chosen channel (step 4) for

that  system.  See  device  installation  manual  for

specific instructions.

7.

Modify the PLM channel setpoint for the PWRcell

inverter  to  match  the  PLM  channel  its  REbus

devices were set to in the previous step.

NOTE: 

Be sure to click Save at the bottom of the menu

after modifying the channel on each device.

8.

De-energize inverter. Once the inverter is de-ener

-

gized, repeat steps 1 – 7.

NOTE: 

 It may take a few seconds for the inverter screen

to power off due to capacitance in the power core. Wait

until  the  screen  goes  blank  before  energizing  the  next

inverter.

9.

After  programming  each  system  separately,  re-

energize all PWRcell inverters by closing their AC

Grid backfeed breakers, enable the inverters, and

all REbus devices.

PLM Crosstalk Recovery Procedure

For each PWRcell Inverter that has crosstalked, perform

the following procedure to clear the foreign devices from

the display after the multi-inverter system has been prop

-

erly commissioned:

1.

De-energize all but one inverter. 

2.

Access  the  Installer  Configuration  Tool  using  the

instructions below. 

3.

Navigate to the Inverter using the Installer Tool and

select PWRcell Configuration. 

4.

Select  Clear  Display  to  wipe  the  screen  of  that

inverter  of  unwanted  devices  from  other  systems

on site.

5.

Follow  steps  1  –  8  for  Multiple  Inverter  System

Commissioning.  See 

Multiple  Inverter  System

Commissioning Procedure

 for more information.

Summary of Contents for PWRcell XVT076A03

Page 1: ...of life This product is not intended to be used in a critical life support application Failure to adhere to this warning could result in death or serious injury Register your Generac product at https pwrfleet generac com 1 888 GENERAC 888 436 3722 Para español visita http www generac com service support product support lookup Pour le français visiter http www generac com service support product su...

Page 2: ...this page See Serial Number Location When contacting an Independent Authorized Service Dealer IASD or Generac Customer Service always supply the complete model number and serial number of the unit Table 1 PWRcell Inverter Important Information Unit Model Number Unit Serial Number Date Purchased Commissioning Date 000393a WARNING CANCER AND REPRODUCTIVE HARM www P65Warnings ca gov ...

Page 3: ... Accessing Wiring Compartment 14 Knockout Dimensions and Locations 14 Wiring Guidelines 15 Grounding Bar Wiring 16 DC Wiring 17 AC Wiring 17 Protected Load 18 Current Transformers CTs 20 Other Accessories 24 Section 6 Commissioning and Setup System Configuration 25 General Information 25 Commissioning the System 25 Registration 25 Connecting PWRcell Inverter to AC Power 26 Selecting Inverter Syste...

Page 4: ...iv Owner s Manual for Generac PWRcell Inverter This page intentionally left blank ...

Page 5: ...ry possible cir cumstance that might involve a hazard The alerts in this manual and on tags and decals affixed to the unit are not all inclusive If using a procedure work method or operating technique that the manufacturer does not spe cifically recommend verify that it is safe for others and does not render the equipment unsafe Throughout this publication and on tags and decals affixed to the uni...

Page 6: ... 000187 WARNING Electrocution Potentially lethal voltages are generated by this equipment Render the equipment safe before attempting repairs or maintenance Failure to do so could result in death or serious injury Risk of injury Do not operate or service this machine if not fully alert Fatigue can impair the ability to operate or service this equipment and could result in death or serious injury 0...

Page 7: ... damage DANGER 000145 DANGER Electrocution In the event of electrical accident immediately shut power OFF Use non conductive implements to free victim from live conductor Apply first aid and get medical help Failure to do so will result in death or serious injury 000599 Electrocution Turn battery disconnect OFF and de energize REbus before touching terminals Failure to do so will result in death s...

Page 8: ...Safety Rules General Information 4 Installation Manual for Generac PWRCell Inverter This page intentionally left blank ...

Page 9: ...0 Output power factor rating AC 1 Operating voltage range AC XVT076A03 L N V rms 108 120 130 Operating voltage range AC XVT076A03 L L V rms 216 240 260 Operating voltage range AC XVT114G03 L N V rms 108 120 130 Operating output voltage range AC XVT114G03 L L V rms 184 208 228 Continuous output current AC grid tied A rms 32 PCS controlled current grid tied A rms 32 Continuous output current AC isla...

Page 10: ...inverters disconnect from the grid and provide AC power to support protected loads when configured to do so This capability is referred to as islanding All PWRcell products use the REbus 380 VDC nanogrid to connect to each other The REbus nanogrid automates the flow of power to enable plug and play setup and operation of PWRcell equipment For more information about REbus visit www generac com In F...

Page 11: ... specific fault detected Inverter LED Inverter LED D communicates the status of the utility grid and or inverter through LED color and state Green utility is connected and within normal operational voltage and frequency Yellow utility grid is not within normal conditions and the inverter is in a waiting state User intervention typically is not required The inverter will restart as soon as the util...

Page 12: ...still be energized unless the building AC disconnect or main service breaker is shut off To enter shutdown press and hold shutdown button E In shutdown mode PWRcell inverter will stop sourcing power to REbus and immediately disable all communicating power sources on REbus by sending a system wide system mode change signal NOTE Successful signal transmission relies upon proper configuration of PLM ...

Page 13: ... units connected to that disconnect NOTE If an additional DC disconnect is added ensure the disconnect switch is DC rated for a minimum of 30 amperes 450 volts To initiate the PVRSS Open the inverter lid Locate the four DC disconnects to the left of the Generac Power Core Turn all disconnects with connected PV sources to the off position PV Links will open all SnapRS devices within 30 seconds cont...

Page 14: ...itions result in a 300 second restart delay time after the trip threshold has been exceeded for the listed number of cycles Frequency Trip Thresholds See Table 3 2 for the default fixed frequency trip set points All over frequency and under frequency trip condi tions result in a 300 second restart delay time after the trip threshold has been exceeded for the listed number of cycles Value of 999 in...

Page 15: ...ces Figure 4 1 PWRcell Inverter Dimensions and Mounting Clearances Mounting Bracket Dimensions Figure 4 2 Mounting Bracket Dimensions 4 in 10 16 cm 28 in 71 15 cm 8 in 20 32 cm 28 1 2 in 72 4 cm 36 in 91 44 cm 8 in 20 32 cm 19 1 4 in 48 9 cm 8 1 2 in 21 6 cm 20 in 50 8 cm 8 in 20 32 cm 24 1 2 in 62 23 cm 010508 16 in 40 64 cm 1 1 2 in 3 81 cm 2 3 8 in 6 03 cm 009990 ...

Page 16: ...he wall Fasteners must be suitable for the mounting surface Fasteners must engage at least two studs or other structural members Mounting bracket has clearance holes for 1 4 in fasteners with slots to accommodate different stud spacings 3 See Figure 4 3 Insert mounting bracket tabs A into inverter body slot B NOTE Figure 4 3 is for illustration purposes only Figure 4 3 Mounting Inverter onto Brack...

Page 17: ...connects H Authorized Generac Personnel Only B REbus Bi directional DC Terminals I STOP Terminals C Internet Connection J Protected Loads Disconnect D DC Main Fuses K AC Grid Connection Terminals E Current Transformers CTs Accessory Ports L Protected Loads Terminals F Automatic Transfer Switches ATS Accessory Port M Grounding Bar G REbus Beacon Port N RGM PWR Gen Inhibit B C D M L K J I H G F E A ...

Page 18: ... is intended only for mounting an optional LTE modem antenna See Figure 5 3 for knockout locations and Table 5 3 for available knockout sizes and quantities When using knockouts Install reducing washers to accommodate smaller conduit sizes Install rain tight or wet locations hubs in compliance with UL514B 000600 DANGER Electrocution Initiate a system wide shutdown and turn the PWRcell DC Disconnec...

Page 19: ...ls as specified in Table 5 4 42 mm 1 21 32 in 50 mm 1 31 32 in 137 mm 5 13 32 in 97 mm 3 13 16 in 140 mm 5 17 32 in 2 13 16 in 72 mm 56 mm 2 7 32 in 40 mm 1 19 32 in 552 mm 21 23 32 in 50 mm 1 31 32 in 45 mm 1 3 4 in 55 mm 2 5 32 in 55 mm 2 5 32 in 26 mm 1 in 58 mm 2 9 32 in 62 mm 2 7 16 in 50 mm 1 31 32 in 48 mm 1 7 8 in 55 mm 2 5 32 in 55 mm 2 5 32 in 35 mm 1 3 8 in 10 mm 13 32 in 28 mm 1 3 32 i...

Page 20: ...g wires are used as communications wires Ensure the following REbus devices have a low resistance wired connection back to the inverter grounding terminal bar PV Link PWRcell batteries Torque all terminals as specified in Table 5 5 Table 5 4 Terminal Torques Wiring Terminal Torque AC terminals 13 3 to 15 9 in lb 1 5 to 1 8 Nm DC terminals 12 in lb 1 35 Nm Ground terminals 4 to 6 AWG 45 in lb 5 Nm ...

Page 21: ...Terminals 000686a DANGER Electrocution Never touch terminals when inverter and PWRcell DC disconnects are ON Doing so will result in death or serious injury 000646 Equipment damage Obey polarity markings when connecting REbus devices Reverse polarizing DC circuits could result in equipment or property damage WARNING 000645 WARNING Equipment damage Do not connect raw unregulated battery output to i...

Page 22: ...bpanel Connect this subpanel to the protected loads terminals The protected loads output can provide on the order of 8 kW of continuous power See Specifications for exact values The inverter can surge up to 50 A for motor starting capabilities NOTE Actual power output for protected loads during a grid outage will depend on system sizing for batteries and solar array NOTE Backup power ratings are s...

Page 23: ...e is expected in the future install a protected loads panel during inverter installation The protected loads panel will be fed by the grid while the system operates in Grid Tie mode Figure 5 6 Configuration for Adding Batteries Later A B C D E 009998 G A PV Array B PWRcell Inverter C Protected Loads Panel D Protected Loads Disconnect E AC Main Panel G Utility ...

Page 24: ...ends using a hardwired connection to provide Internet connectivity Generac does not support using any wireless or power line carrier network devices Use these devices at your own discretion NOTE Ethernet cable run must be dedicated for the inverter This cable may not be daisy chained to another device including another PWRcell inverter Current Transformers CTs Current transformers CTs are required...

Page 25: ...re multiple sets of CTs to fully measure the utility power being sent to the building For 4 wire 120 240 VAC split phase service Use two pairs of CTs to measure the service Use each pair of CTs to measure a pair of service conductors feeders within the main panel Use both RJ 45 jacks with two Cat 5 cables Connect CT1 from both cables to the same phase and CT2 cable from both cables to the second p...

Page 26: ...ion may not be necessary or desirable To daisy chain a CT signal 1 Connect and calibrate a set of CTs to the first inverter See CT Calibration for more information 2 Run a new Cat 5 cable between the spare CT accessory port of the first inverter to either CT accessory port on the second inverter NOTE Running a new Cat 5 cable between inverter CT ports prior to calibration in Step 1 may cause calib...

Page 27: ...T calibration Check wiring and CT integrity ct cal 5 0x8065 Line 1 3 don t have a valid CT calibration Check wiring and CT integrity ct cal 6 0x8066 Line 2 3 don t have a valid CT calibration Check wiring and CT integrity ct cal 7 0x8067 Line 1 2 3 don t have a valid CT calibration Check wiring and CT integrity ct cal 9 0x8069 Line 1 has multiple CTs on it or a CT is on the neutral wire Check wiri...

Page 28: ...re When no LTE Modem is installed the power cable will be left unconnected and safely secured Complete installation instructions are included in the LTE Modem Kit Order part number PCLTE1 Technical Service Connection Service RJ 11 jack C is for use by authorized Generac personnel only Never connect any device to this jack without direct instructions from Generac Technical Service Figure 5 10 Acces...

Page 29: ...nnected devices are turned ON Commissioning consists of seven steps 1 Register system 2 Energize the PWRcell inverter with AC power 3 Select Inverter system mode 4 Configure inverter settings 5 Select inverter compliance setting optional 6 Select ESS Grid Usage Mode optional 7 Enable REbus devices 8 Test islanding Registration NOTE If the system will not be connected to the Inter net installer wil...

Page 30: ...See Figure 6 3 A list of system modes will be displayed with the current mode marked with an asterisk NOTE The list of modes may not include all those shown in Figure 6 3 Figure 6 3 Selecting System Modes 1 of 4 3 See Figure 6 4 Use the up and down arrows to highlight the desired mode and press the center button to select Figure 6 4 Selecting System Modes 2 of 4 4 Arrow right and press the center ...

Page 31: ...12 1 Channel for REbus communications All devices in a system must use the same channel except REbus Beacon Do not set equipment to channel 0 unless performing Multiple Inverter System Commis sioning Procedure TargMaxImprtP 30 000 to 30 000 Watts 0 Maximum Threshold for importing power before the battery will dis charge in Self Supply Mode to offset TargMinImprtP 30 000 to 30 000 Watts 0 Minimum p...

Page 32: ... loads as well as sup plying power to a utility when connected See Setting for Import Export Compliance for more information Export Limiting mode allows the user to restrict the export to a connected utility grid to a Export Limit value set by the installer When the Export Limit value is set to 0 this mode functions as like a Zero Export mode CRD200 Import Only compliance allowing the battery to b...

Page 33: ...acon Configuring and Running a TOU Schedule 1 See Figure 6 11 Navigate to the Beacon device page and press the center button to enter the device menu Figure 6 11 Configuring TOU Schedule 1 of 4 2 See Figure 6 12 Use the up and down arrows to highlight Mod Settings and press the center button to enter the settings menu Figure 6 12 Configuring TOU Schedule 2 of 4 3 See Figure 6 13 Use the up and dow...

Page 34: ...nd Figure 6 16 When enabled the LCD will alternate between a TOU Scheduler Running Screen and a Current System Mode screen Both screens will display the time until the next system change and the mode the system will change to The TOU Schedule name will be listed at the bottom of the device page Figure 6 15 Running Figure 6 16 Current System Mode See Figure 6 17 and Figure 6 18 On the home page the...

Page 35: ...e device menu Figure 6 21 Disabling Beacon 1 of 3 2 Highlight Disable and press the center button 3 See Figure 6 22 Arrow sideways to Confirm and press the center button Figure 6 22 Disabling Beacon 2 of 3 4 See Figure 6 23 The status line on the Beacon device page will read Disabled NOTE The system will remain in the current system mode until the mode is changed manually or the sched uler is re e...

Page 36: ...n 2 Navigate to the system home page and change the system mode to a backup only mode such as Pri ority Backup or Clean Backup See the Generac PWRcell Inverter Owner s Manual for more infor mation on system modes 3 Once the emergency has passed re enable the scheduler See Enabling Beacon TOU for more information NOTE If Priority Backup mode is not listed with the other system modes the system inst...

Page 37: ...et Settings Figure 6 28 Ethernet Troubleshooting NOTE Ensure blue Cat 5 cable is reconnected to the Beacon after troubleshooting is complete On the Ethernet settings page the PWRview State should read Listen then a successful connection has not been made to the PWRview server If the inverter does not automatically connect to the network and begin communicating with the PWRview server perform the f...

Page 38: ...eed to be restarted for the cross talked inverters 1 Close the AC backfeed breaker to supply AC power to one PWRcell Inverter AC Grid Input Out put Terminals This will allow the inverter to ener gize and illuminate the Inverter control panel 2 Perform Commissioning the System steps 1 7 3 Modify the PWRcell inverter PLM Channel to 0 NOTE PLM Channel 0 is a catchall channel Only use for inverters du...

Page 39: ...r can be found on the front of the Beacon located inside the inverter as well as on the Beacon device page through the inverter s screen To find this number through the inverter s screen press the center button on the Beacon device page The RCP number will be displayed at the bottom of the menu screen 4 Type in the password labeled CODE for the REbus Beacon s Wi Fi network NOTE The code for the RE...

Page 40: ...inverter software version in the Beacon Installer Tool select the Common sub menu option under the Inverter object as shown in Fig ure 6 31 Figure 6 31 Verifying Inverter Software The information populated upon selecting the Common sub menu option lists the manufacturer model version and serial number for the inverter The value displayed for Version contains the hardware version and software versi...

Page 41: ...ettable Please be aware that once set certain Utilities may require the request to unset this setting come from the Utility To unset Zero Import please contact Generac PWRcell Technical Sup port Changing the value from DISABLED to ENABLED via the dropdown list will prevent the PWR cell batteries from importing power from the utility grid NOTE This feature is only available for inverter firmware ve...

Page 42: ...the In compliance with line in the PDF If your utility requires proof of correct configuration save this PDF and send it to your utility It is recommend you keep a copy on file as well 1 To generate a proof of compliance PDF click on the Compliance PDF tab in the navigation menu 2 Click on Download Report 3 A new window will open in the browser with the report Verify information is correct and sav...

Page 43: ...ects See PWRcell Inverter Wiring Compartment for location If a main fuse has blown determine the root cause of the issue before replacing it For assistance contact the nearest Independent Authorized Service Dealer IASD contact Generac PWRcell Technical Support at 1 855 635 5186 or call or Generac Customer Service at 1 888 436 3722 1 888 GENERAC or visit www generac com 000642 DANGER Electrocution ...

Page 44: ...lder up and turn counterclockwise to release 8 Remove fuse from fuse holder and check for conti nuity using a multi meter 9 Insert replacement fuse into fuse holder 10 Reinstall fuse holder Turn clockwise until tight Figure 7 2 Removing Wiring Compartment Cover Recovery From an Error State Error events will force the PWRcell inverter into an error state where no DC power is exported though voltage...

Page 45: ...er is in place between STOP terminals CTs will not calibrate Loose connection Check CT wiring Trigger manual CT calibration from the inverter device menu No REbus Beacon device page Beacon USB cable not connected Verify the USB cable is correctly connected to the Beacon and also to the Beacon accessory port in the inverter wiring compartment Inspect exposed sections of cable for damage Beacon wrap...

Page 46: ...Troubleshooting 42 Installation Manual for Generac PWRCell Inverter This page intentionally left blank ...

Page 47: ...This page intentionally left blank ...

Page 48: ...rights reserved Specifications are subject to change without notice No reproduction allowed in any form without prior written consent from Generac Power Systems Inc Generac Power Systems Inc S45 W29290 Hwy 59 Waukesha WI 53189 1 888 GENERAC 1 888 436 3722 www generac com ...

Reviews: