Operator's Manual
Second Edition • Second Printing
32
Genie TMZ-50/30
Part No. 114255
OPERATING INSTRUCTIONS
Material Lifting Configuration
Observe and Obey:
Maintain safe distances between the operator,
machine and fixed objects.
Be aware of the direction the boom will travel
when using the platform controls.
Material Lifting Configuration
Set up
1 Turn the key switch to the off position.
2 Remove the pin that secures the material lifting
hook to the base. Remove the material lifting
hook.
3 Disconnect the platform controls from the
platform.
4 Remove the platform controls. Open the clamp
on the back of the platform controls and slide
the controls up and off.
5 Open the controls side turntable cover.
6 Disconnect the electrical cord on the bottom
right side of the ground control box. Connect
the platform control cord disconnected in step 3
to the ground control box. Close the turntable
cover.
7 Support the platform. Remove the toggle pin
that secures the platform to the jib boom.
8 Lift the platform up and remove it from the
machine.
9 To install the material lifting hook, insert the
bottom rail into the platform mounting bracket
and rotate up into position. Insert the toggle
pin.
10 Operate the material lifting hook from the
ground with the platform controls. The key
switch should be turned to the platform control
position.
11 Reverse the above process to install the
platform and return the machine to a personnel
lifting configuration.