3 - 10
Z-30/20N • Z-30/20N RJ • Z-34/22 • Z-34/22N
Part No. 139378
Section 3 • Scheduled Maintenance Procedures
June 2011
REV B
Checklist B Procedures
B-1
Inspect the Battery
Genie requires that this procedure be performed
every 250 hours or quarterly, whichever comes
first.
Proper battery condition is essential to good
machine performance and operational safety.
Improper fluid levels or damaged cables and
connections can result in component damage and
hazardous conditions.
Electrocution/burn hazard. Contact
with electrically charged circuits
could result in death or serious
injury. Remove all rings, watches
and other jewelry.
Bodily injury hazard. Batteries
contain acid. Avoid spilling or
contacting battery acid. Neutralize
battery acid spills with baking soda
and water.
1 Put on protective clothing and eye wear.
2 Be sure that the battery cable connections are
free of corrosion.
Note: Adding terminal protectors and a corrosion
preventative sealant will help eliminate corrosion on
the battery terminals and cables.
3 Be sure that the battery retainers and cable
connections are tight.
5 Be sure that the battery retainers and cable
connections are tight.
4 Fully charge the battery. Allow the battery to
rest 24 hours before performing this procedure
to allow the battery cells to equalize.
5 Remove the battery vent caps and check the
specific gravity of each battery cell with a
hydrometer. Note the results.
6 Check the ambient air temperature and adjust
the specific gravity reading for each cell as
follows:
•
Add 0.004 to the reading of each cell for
every 10° / 5.5° C above 80° F / 26.7° C.
•
Subtract 0.004 from the reading of each cell for
every 10° / 5.5° C below 80° F / 26.7° C.
Result: All battery cells display an adjusted
specific gravity of 1.277 +/- 0.007. The battery
is fully charged. Proceed to step 10.
Result: One or more battery cells display a
specific gravity of 1.269 or below. Proceed to
step 7.
7 Perform an equalizing charge OR fully charge
the batteries and allow the battery to rest at
least 6 hours.
8 Remove the battery vent caps and check the
specific gravity of each battery cell with a
hydrometer. Note the results.
Summary of Contents for Z-30/20N
Page 1: ......
Page 148: ...6 46 June2011 Section 6 Schematics 6 45 Power Cable Wiring Diagram...
Page 149: ...6 47 Section 6 Schematics June2011 6 48 Drive Contactor Panel Wiring Diagram...
Page 152: ...6 50 June2011 Section 6 Schematics Manifold and Limit Switch Wiring Diagram 6 49...
Page 153: ...6 51 Section 6 Schematics June2011 6 52 LVI BCI Option Wiring Diagram...
Page 156: ...6 54 June2011 Section 6 Schematics 6 53 Charger Interlock Option...
Page 157: ...6 55 Section 6 Schematics June2011 6 56 CTE Option CE Models...
Page 160: ...6 58 June2011 Section 6 Schematics Hydraulic Schematic 6 57...