Gentherm Global Power Technologies 13-1
P-5050
62553 Rev.8
13 Heat Recovery System (HRS) Option
13.1 Introduction
The Heat Recovery System (HRS) Option is available for P-5050 and P-5100. This option allows
for waste heat recover, to warm building interiors where required, see Figure 39.
The TEG configured for the HRS application includes an HRS specific rain cap, exhaust tube as-
sembly, and burner configuration. The ducts and legs are replaced with mounting bars for mount-
ing to the HRS option, see Figure 40, Item G37.
13.2 Installation
Each HRS kit is provided with an installation manual to provide instruction for mounting the HRS
to the exterior wall of the building. Refer to the Heat Recovery System (HRS) Installation Manual,
part number 3900-66683 to complete the HRS and TEG installation.
WARNING: Do not block air flow to duct openings. Doing so may cause over
temperature as well as damage to TEG.
Figure 39
HRS Option Overview.
Summary of Contents for P-5050
Page 4: ......
Page 8: ......
Page 44: ...Gentherm Global Power Technologies 5 12 P 5050 62553 rev 8 ...
Page 46: ...Gentherm Global Power Technologies 6 2 P 5050 62553 rev 8 ...
Page 60: ...Gentherm Global Power Technologies 8 10 P 5050 62553 rev 8 ...
Page 98: ...Gentherm Global Power Technologies 14 4 P 5050 62553 rev 8 ...