STAKE-OUT DEPENDING ON THE TERRAIN
GENERAL STAKE-OUT PRINCIPLES
Position of the structure
Proven simulation programs are available for determining the optimum position of the structure. Unfavourable lo-
cations with large jump heights or terrain shadows are detected.
Structure line
In principle, you must plan the line of the structure so that is as straight and horizontal as possible. Wherever
possible, avoid or compensate for irregular line routing, and depressions or bulges in the terrain between posts.
Placing foundations
The base plates of the foundation must be laid so that the lower support rope is kept as close to the ground as
possible.
The base plates must be placed so that the lower support rope is routed along the edges of the foundation and
does not damage them.
Summary of Contents for GBE-100A-R
Page 2: ...Page 2 48 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 100A R 08...
Page 3: ...Page 3 48 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 100A R 08...
Page 45: ...Page 45 48 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 100A R 08...
Page 46: ...Page 46 48 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 100A R 08...
Page 47: ...Page 47 48 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 100A R 08...