Page 20/43
© Geobrugg AG, CH-8590 Romanshorn, Switzerland
GBE-3000A / 16
ROCK:
•
Level the rock 0° - 30° from horizontal underneath the base
plate
29
•
Drill into rock
112
the two holes perpendicular to the base
plate
29
•
Grout in the anchors
08
, the calculation of the anchor length
is set by the project engineer
•
A thin levelling layer ensure a stable placement of the base
plate
•
Position base plate
29
into levelling layer
•
Fasten the nuts
10
until an initial tensile force of approx. 30
kN is reached
Tightening torque for nuts to reach an initial tensile force of approx. 30 kN:
Swiss GEWI NG 28
Swiss GEWI NG 32
Tightening torque
400 Nm
400 Nm
Frost and icing-salt resistant mortar has to be used
Reinforcement: 12 mm-rod diameter in distance of 150 mm
If requested an installation template can be supplied.
It is important to ensure that the anchors have sufficient contact with the mortar and make good bond,
and a sufficient area to the surrounding material.
Further information about the anchoring of the base plate can be found on the anchor forces date sheet.
The forces that occur during a rockfall event are not to be underestimated. The civil engineering and in-
stallation work must therefore be carried out by professionals.
.
08
29
09,10
112
09,10
Summary of Contents for GBE-3000A
Page 2: ...Page 2 43 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 3000A 16...
Page 3: ...Page 3 43 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 3000A 16...
Page 41: ...Page 41 43 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 3000A 16...
Page 42: ...Page 42 43 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 3000A 16...
Page 43: ...Page 43 43 Geobrugg AG CH 8590 Romanshorn Switzerland GBE 3000A 16...