NOTE:  Contact Giant Industries for Service School Information.  Phone:  (419)-531-4600.

Operation and Maintenance

Check oil level prior to starting and ensure trouble-free water 

supply.

Oil:

  Use only 1.6 gallons (6.0 liters) of SAE 80W-90 Industrial 

Gear Lube Oil (Giant’s p/n 01154).  

IMPORTANT! 

If the pump is mounted on a vehicle with the 

possibility of unlevelness and/or the pump speed is between 

300 & 500 RPM, the volume of oil should be 2 gallons (7.5 

liters). To check, put the oil dipstick in the bore situated next to 

the eye bolt. 

Initial change after 50 hours and then after every 500 operating 

hours.  If used less than this, change once per year.

IMPORTANT!

  When operating in humid areas (or areas 

with large temperature fluctuations, the oil must be changed 

immediately (if condensate or frothy oil occurs in the 

crankcase).

I

MPORTANT!

  We recommend that both inlet ports be used in 

order to ensure cavitation-free operation and optimal suction 

conditions.  If only one connection is use, a safety margin of 3 

feet (1 meter) has to be added to the required NPSH.

IMPORTANT!

  The GP7645GB, GP7650GB and GP7655GB 

pumps have a black arrow on the reduction gear, which shows 

the preferred direction of rotation.  The pump  can be delivered 

either with the gear on the left side or right side (when facing 

the front of the pump), which eases planning assembled units 

with regard to the desired direction or rotation.  

In either case, 

the larger gear wheel must rotate towards the front-end of 

the pump.

The preferred/optimal direction of rotation ensures that the oil 

is correctly splashed on the crosshead guides via the motion 

of the connecting rods, which is a particular advantage where 

continuous operation is involved.

The pump can also be run against the recommended direction 

of the rotation if operated periodically or at reduced pressure.  

If this is the case, the pump has to be run in this direction 

to smoothen the bearing areas.  This is done by a one-time 

operation at zero pressure for at least 30 minutes; thereafter, 

the pressure must be slowly increased over the next hour to 

the desired maximum operating pressure.  This should run-in 

the pump, but you should also check the oil temperature, 

which should not exceed 160 

o

 F (71 

o

C).

The torque tension on the valve casing nuts (49A) is to be 

checked after approximately 200 hours.  Please see page 6 for 

torque values.

IMPORTANT!

  The service life of the seals is maximized if a 

minimal amount of leakage is present.  A few drops of water 

can drip from each plunger every minute.  Leakage has to 

be examine every day.  If the leakage becomes excessive 

(constant dripping), the plunger seals must be changed.

Safety Rules

The operating instructions must be read and adhered to 

before performing any work on the pump or complete 

assembled unit.  No responsibility will be carried by us 

for damage to materials or persons

 

caused by improper 

handling of our pumps

.

Access to the pump is not allowed by unauthorized personnel.  

As safety valve is to be installed in accordance with the 

guidelines for liquid spraying units, so that the admissible 

operating pressure cannot be exceeded by more than 10%.  

Pumps operating without a safety valve as well as any excess 

in temperature or speed limits automatically voids the warranty.  

When the pump is in operating, the exposed shaft side, the driven 

shaft side and its coupling must be covered by a protective guard.  

The plunger area must also be covered by the protective plate 

(30).  Do not step onto the protective plate (30 ) or put weight on 

it.

Before carrying out any maintenance work to the pump or pump 

unit, the pressure in the discharge line and pump must be at zero.  

Close off the suction line.  Disconnect fuses to ensure that the 

driving motor cannot accidently get switched on.  Before starting 

the pump, make sure that the pump, the cooling system and all 

parts on the pressure side of the unit are vented and refilled with 

pressure at zero.

In order to prevent air or air/water-mixture being absorbed and 

cavitation occurring, the pump NPSHR (Net Positive Suction 

Head Required) and water temperature must be adhered to.

Cavitation and/or compression of gases lead to 

uncontrollable pressure kicks, which can ruin the pump and 

unit parts and also be dangerous to the operator or anyone 

standing nearby.

Giant plunger pumps are only suitable for pumping fresh clean 

water.

Cooling the Gear Oil

IMPORTANT! 

 The water input pressure must not exceed 29 PSI 

(2 bar) when using the integrated system for cooling the gear oil 

(standard version). 

If a separate cooling circuit (maximum 29 PSI [2 bar]) is installed, 

it is then possible to have an input pressure of up to maximum 

145 PSI (10 bar) on the suction side.

Make sure that suction pulsation is sufficiently dampened - water 

column resonance must be avoided.

IMPORTANT!

  The pumps can be run without gear oil cooling in 

continuous operation 

up to

 a power rating of 

80 hp (60 kW)

 or 

with major intermittent operation).

If operation power 

exceeds 80 hp (60 kW)

 or if continuous 

operation is the case, the pump must be run with the integrated 

oil cooling system.  The maximum temperature of the water 

being pumped and which is also fed through the cooling system 

must not exceed 86 °F (30°C).  The amount which is fed into the 

cooling system depends on the pump speed and is approximately 

1.5 GPM (5.5 L/min) at 800 RPM.  The cooling water is sucked in 

by one of the pumping chambers and pumped away.

IMPORTANT! 

 The pump and cooling system must be emptied if 

there is a danger of frost.  Note that travel wind can cause water 

in pumps fitted on open vehicles to freeze even if the outside 

temperature is above freezing point.

To empty the colling circuit, remove the L-joints (K11) on the 

pump head (50).  Blow out the circuit liquid (hoses K12) at the 

joint connection (K11/K7) using compressed air.

The torque tension on the valve casing nuts (49A) is to be 

checked after approximately 200 operating hours.  Please refer to 

the section “Maintenance” concerning the torque values.

The pump must be at zero pressure when checking the torque 

tension.

Summary of Contents for GP7645GB

Page 1: ...rts List page 5 Kits page 6 Torque Specifications page 6 Maintenance Information page 6 Repair Instructions page 7 Warranty Information back page Triplex Ceramic Plunger Pump Operating Instructions Repair and Service Manual Models GP7645GB GP7650GB GP7655GB Gearbox Versions for Pinion Shaft Drives Updated 03 22 ...

Page 2: ...o the pump is not allowed by unauthorized personnel As safety valve is to be installed in accordance with the guidelines for liquid spraying units so that the admissible operating pressure cannot be exceeded by more than 10 Pumps operating without a safety valve as well as any excess in temperature or speed limits automatically voids the warranty When the pump is in operating the exposed shaft sid...

Page 3: ...e a pulley diameter one 1 pulley diameter and the required pump RPM must be known Pump RPM x Pump Pulley Diameter Motor RPM Motor Pulley Diameter Motor RPM x Motor Pulley Diameter Pump RPM Pump Pulley Diameter Common Specifications Inlet Pressure w out cooling system 4 35 to 145 PSI 0 3 to 10 Bar Inlet Pressure w cooling system 4 35 to 29 PSI 0 3 to 2 Bar Pinion Shaft Diameter 1 38 35mm Crankcase ...

Page 4: ...4 Exploded View GP7645GB GP7650GB GP7655GB ...

Page 5: ...2 07638 V Sleeve GP7650GB 6 42 07711 V Sleeve GP7655GB 6 43 13293 Pressure Ring GP7645GB 3 43 07639 Pressure Ring GP7650GB 3 43 07712 Pressure Ring GP7655GB 3 ITEM PART DESCRIPTION QTY 45 13297 Tension Spring GP7645GB 3 45 07636 Pressure Spring GP7650GB 3 49 13159 Stud Bolt 8 49A 13160 Hexagon Nut 8 50 07791 Valve Casing 1 50A 13162 Centering Stud 2 51 05594 Inlet Valve Assembly 51A 51F 3 51A 0559...

Page 6: ...charge Valve Kit 09661 Item Part Description Qty 51B 05450 Valve Spring 1 51C 05247 Valve Plate 1 51D 05596 O Ring 1 52F 05599 O Ring 1 56A 07658 O Ring 1 56B 07635 Support Ring 1 The discharge valve seat item 52E can be flipped over and used If it is damaged on both sides order kit 09660 GP7645GB GP7650GB GP7655GB Torque Specifications Position Item Description Lubrication Info Torque Specificati...

Page 7: ...ve the crankcase cover 4 Loosen inner hexagon screws on the connecting rods 24 Note Connecting rods are marked for identification Do not twist connecting rod halves Each connecting rod is to be reinstalled in the same position and orientation on the crankshaft journals Push the connecting rod halves as far into the crosshead guide as possible Take out the bearing cover 14 TO DISMANTLE REDUCTION GE...

Page 8: ... the product as a component part 5 Changes or modifications made by the customer or third party 6 The operation of pumps and or accessories exceeding the specifications set forth in the Operations Manuals provided by Giant Industries Inc Liability under this warranty is on all non wear parts and limited to the replacement or repair of those products returned freight prepaid to Giant Industries whi...