4
1.2 Compliance
The LCR-600 is CE compliant.
2
Product Contents and Inspection
This unit is tested prior to shipment. It is therefore ready for
immediate use upon receipt. An initial physical inspection should be
made to ensure that no damage has been sustained during
shipment.
Inspect the packing box on receipt for any external damage. If
any external damage is evident, remove the instrument and visually
inspect its case and parts for any damage. If damage to the
instrument is evident, a description of the damage should be noted
on the carrier’s receipt and signed by the driver or carrier agent.
Save all shipping packaging for inspection. Forward a report of any
damage to the agent through which the unit is procured.
Retain the original packing in case subsequent repackaging for
return is required. Use of the original packing is essential.
After the mechanical inspection, verify the contents of the
shipment. The items included in this package are:
•
LCR Meter
•
Power Cord
•
User
Manual
•
BNC Plug to Clip
Lead Wire