7 On-Roof Installation
Diagram 7.5
15181
With regards to the hydraulic system you have chosen, insert
and secure the hydraulic connections, see diagrams 7.5 and
7.6.
Connect the collector Flow and Return to the system circuit.
Ensure that all of the following steps have been performed:-
- All the connections have been fixed with securing clips.
- All hydraulic connections laid properly.
- The collector sensor has been connected.
- The collectors are connected to a lightning protection
device.
- A pressure test carried out and all connections are tight.
- All insulation is intact.
NOTE:
After initial commissioning and according to the
season, high outside temperature oscillations can cause
condensation in the collector, this is normal.
Diagram 7.6
15182
COLLECTOR SENSOR
COLLECTOR SENSOR
1 - 5 Collectors
6 or more Collectors