At least two persons are required for this operation. See illustration oppostie.
•
Place the machine in its final position.
•
Open the locks
(1)
.
•
Mount the bearings on the rollers ensuring that
–
the bearings with the small springs
(2)
are installed on the lower gum section
roller
(3)
and on the lower exit roller
(4)
. Normally the brushes are already
installed, but if not, make sure that all rollers
(5)
below the brushes are also fitted
with the bearings/springs
(2)
.
–
the bigger springs
(6)
and washers
(7)
must be installed between the rollers and
bearings in the end opposite the drive gears on the gum section rollers
(3)
and
(8)
.
•
Lower the rollers into the grooves and then close the locks
(1)
.
Installation Manual - Plate Processor 150
1049
2-18
Installation
Preparation for processing