Part 2: Installation
Installation hours
How many working hours are planned for the installation?
Installation hours for off-line machine:
•
Provided the machine is unpacked and will stay in the room and all electrical, water
and drain installations are in place, the estimated installation time is 4 – 5 hours .
•
If the machine must be disassembled to get into the room before installation
add another 4 - 5 hours for disassembling and reassembling.
•
Unpacking and transportation from pallet to the floor, add 2 – 3 hours.
Standard installation hours for on-line machine:
•
Provided the machine is unpacked and will stay in the room and all electrical, water
and drain installations are in place, the estimated installation time, including
interface installation and connection to the setter, is 6 – 8 hours.
•
If the machine must be disassembled to get into the room before installation
add another 4 - 5 hours for disassembling and reassembling.
•
Unpacking and transportation from pallet to the floor, add 2 – 3 hours.
Customer training hours
How many working hours are planned for training the customer?
•
Introduction and training of the customer (daily user) in normal use of the
processor, operating, etc., is estimated to 2 – 3 hours.
•
Training of the customer (daily user) in normal daily cleaning and maintenance is
estimated to 2 – 3 hours.