20
DEFLATION
If the punch or pressing operation is interrupted, then it is likely that the rubber bellows may remain inflated. Use
the rightmost button to select the DEFLATE operation. Now press the center button and the bellows will start to
deflate. The process takes about 20 to 30 minutes.
For safety reasons deflation can only be performed using the local controller panel. The App CANNOT initiate
the DEFLATE operation.
THE CLEAR LID ENABLES YOU TO CHECK IF THE BELLOWS ARE INFLATED. DO NOT ATTEMPT TO OPEN THE LID
CLAMP IF THE BELLOWS ARE VISIBLY PRESSURIZED. THIS MAY CAUSE THE LID AND/OR CLAMP TO OPEN IN A
VIOLENT MANNER AND MAY CAUSE DAMAGE OR INJURY. ONLY OPEN THE LID CLAMP WHEN THE BELLOWS AND
FERMENTATION LINER ARE COMPLETELY DEFLATED.
Push button to
select DEFLATE
OPER should be
DEFLATE
Press START to
begin DEFLATION