3.Once the feet are fixed, the Battery Enclosure is ready for installation as shown in Figure 4.

Note: 

The battery switch should remain off during the installation process.

The enclosure can be used to house Li-ion battery types,the following installation uses GoodWe 

SECU-A battery as an example.

. Up to two GoodWe SECU-A (4.8kWh) battery packs with a total storage capacity of 9.6 kWh.
1.Insert the batteries onto the shelves one at a time by inserting the battery pack bottom first into 

the cabinet. Please fill the cabinet from bottom to top,  insert battery 2 first ,then 1 (see figure 
8). 

Figure 6: GoodWe SECU-A battery front handles.

Figure  7:  BCL0096  with  the  bottom  battery 
inserted

Figure  8:  Inside  view  of  BCL0096  with  two 
GoodWe SECU-A batteries.

2.Once the batteries are placed into position, plug the respective power leads into the power 

connectors on the batteries while taking note of the polarity. Ensure that the battery 2 lead 
which has the power connector for the Fan Controller is plugged into one of the batteries.

Figure 4: Battery Enclosure with the feet attached and ready for installation.

Figure 5: BCL0096 wall mounting holes.

3.Once the enclosure is fixed onto the wall, apply generous amount of the supplied sealant on the 

six screw holes to seal off any moisture ingress points.

Inserting the batteries

Mounting the enclosure

   The Battery Enclosure is designed to be installed below the Inverter and comes prewired for easy 

integration with GoodWe Inverter.

1.Set the Battery Enclosure against the wall. Ensure that the floor where the Battery Enclosure is 

to be installed is level.

2.Use the supplied fixing screw and plug set to fix the enclosure onto the wall. An alternative fixing 

mechanism can be employed if the supplied screw and plug set is not appropriate for the wall.

05

06

Summary of Contents for BCL0096

Page 1: ...Installation Manual Smart Hybrid Battery Enclosure BCL0096 V1 0 340 00429 00...

Page 2: ...968 No part may be reproduced by any process nor may any other exclusive right be exercised without the permission of GoodWe Technologies Limited Privacy notice GoodWe will use the information provide...

Page 3: ...he location selected for the Battery Enclosure installation There should be ample room min 150mm for air circulation around the Battery Enclosure as the Battery Enclosure uses fans to circulate air th...

Page 4: ...width 535mm depth 280mm height 1205mm with the feet installed Figure 1 Dimensions Figure 2 BCL0096 out of the packing box Figure 3 Battery Enclosure feet and mounting screws 1 In preparation for the i...

Page 5: ...he respective power leads into the power connectors on the batteries while taking note of the polarity Ensure that the battery 2 lead which has the power connector for the Fan Controller is plugged in...

Page 6: ...y is as follows GoodWe SECU A 2x earthing points 2x earthing points 2x earthing points Side of Battery Enclosure wire frame view 2x earthing points Fan Controller Front view of Battery Enclosure DIP S...

Page 7: ...of the master battery Master battery COM 1 port to Inverter port Link port COM 1 of the slave battery From To Cable label APP Setting On PV Master To make sure the battery communicates to inverter un...

Page 8: ...BoS box and the Battery Enclosure s front cover still open turn on the Invert er and subsequently close the battery breaker in preparation for the commissioning process CAUTION GoodWe Battery SECU A 1...

Page 9: ...Notes 13...

Reviews: