8A.8
The selected cable connectors can be installed in the appropriate junction boxes and the
cable connected.
8A.9
Repeat the above stops as necessary for second C-track.
STEP 8B - TOP FLANGE C-TRACK FESTOONING INSTALLATION (OPTIONAL)
8B.1
Divide total length of beam by 5’-0”. This will gaive equal number of spaces of cross arm
support brackets. The remainder should be divided equally among each end.
8B.2
Measure the distance from the end of Tarca® track from Step 8B.1 above and install first
cross arm support piece. Secure on each side of top flange with beam clamp and
hardware. Remaining cross arm supports to be installed at 5’-0” increments along top
flange of rail.
8B.3
Bolt track hangers loosely to cross arm supports, while sliding each 10’-0” long section of
C-Track into place. Start at one end of system.
8B.4
Install track joints as required. They will support the adjacent sections of track. After all
track sections and hangers are in place, secure all fasteners.
8B.5
Install festoon end clamp and hanger endstop to one end of system.
8B.6
Install cable trolleys into track system. If it is convenient, cables may be installed into
trolleys on the floor, establishing correct size of loops and tie wrap cables as needed.
14
9/18 Rev. F
Diagram 8C.
Top Flange C-Track Festooning.