Select
Select
Select aa
a Location
Location
Location
When selecting a location for the STU assembly,
make sure the location:
• Is close to where the fluid is being delivered
to minimize back pressure and maximize flow
rate.
• Provides enough room around the equipment
for maintenance.
• Does not interfere with opening the control
panel door or frame door (on one or both
sides).
• Provides enough room on the right and/or
left side of the SaniForce STU to easily load
and unload fluid totes with a forklift or pallet
jack hand truck.
• Provides easy and safe access to the air supply
shutoff valves and the control panel. Graco
recommends a minimum of 3 ft (0.91 m) of
open space in front of the panel.
• Provides enough overhead clearance (10
ft, 2.7 m recommended) for installing and
servicing the STU.
• Has a flat, level floor or level pads.
Move
Move
Move the
the
the Frame
Frame
Frame to
to
to the
the
the Selected
Selected
Selected
Location
Location
Location
The frame is shipped with several major
components attached and weighs about 1500
lb (680 kg). To avoid injury and equipment
damage, follow instructions below.
The STU must be firmly attached to the floor.
The STU is capable of exerting downward
force of 2220 lbf (9.9 kN) which could cause
the STU to lift off of the floor during operation.
• Use a forklift or hand truck and support
devices, such as a hoist, and have an adequate
number of personnel to move the frame to the
installation site.
• Avoid jarring or tilting the frame while moving
it.
• When the fully assembled unit has been
moved to the installation location:
– Mark the location of the mounting foot
holes on the floor.
– Move the frame out of position by rotating
it to the side.
– Drill anchor mounting holes and insert
anchors at all marked foot hole locations.
– Rotate the frame back into position and
install frame mounting bolts through the
frame feet.
3A5416L