Should the existing pump or house water system already have a dry run protection
it may be appropriate and is possible to order the Aqua without a dry run
protection.
4.4
Connection of the solenoid valve
Connect the plug of the solenoid valve with the centre coupling
[9]
of the control electron-
ics (see figure
1).
5.
Commissioning
Before the putting the equipment into operation check and be sure that all electrical con-
nections are correctly insulated and all covers are properly closed.
Now open the transparent cover of the system controls. Plug the equipment into the mains
socket (this socket must be exclusively for the equipment and be on its own fuse). The
system then runs a system check through automatically.
For the duration of the system check (approx. 10 seconds) the following signal will be dis-
played in the window:
13
Picture 5: Electrical wiring diagram
Aqua
Sensor pick up
element
Sensor
Data cable
( 12V )
Valve
230V AC
(Net)
Pressure
switch
Pump
Picture 6: Display during the equipment check