Assembling the exterior switch cabinet
63
/
144
Before installation a strip or solid foun-
dation must be prepared.
When the foundation is being cast, the
drawn dimensions must be adhered to,
particularly the position of the hole
through which the hoses will be led
later
Two M10 holes must be made in the
bottom of the cabinet central to the
side walls. These holes must be con-
tinued in the concrete foundation be-
low.
Inserting the M10 dowels into the
holes. Securing the switch cabinet with
the aid of the two M8 screws (together
with washers).
250 mm
M10 holes