131
UCP
-
3901
User Manual
STEP 3: Make a Change to the Video Wall
This sub-section uses uses the GV Orbit Client to get the video wall from a module, make a
change and push it back to the module.
Introduction
This sub-section will:
• Get the Orbit multiviewer project from the Multiviewer SDC. This is the factory default
Get Orbit Multiviewer Project from the Multiviewer SDC
• Make a simple, visible change to the video wall. See
• Push the amended project back to the unit and see the change. See
• Pull a project from the Multiviewer SDC. See
Pull a Project into Orbit from a Device
Assumptions
This sub-section assumes that:
• The UCP
-
3901 is connected to a media network and receiving/sending video IP
streams.
• IP addresses of the UCP
-
3901’s media Ethernet interfaces are known.
• Orbit is installed on a client computer connected to the media network. (
Note:
A Orbit
license is not required for basic GV Orbit operation.)
Get Orbit Multiviewer Project from the Multiviewer SDC
To get the Multiviewer SDC’s Orbit multiviewer project:
1 Run Orbit and click
File > New project
.
Fig. 6-4: Orbit File > New Project
2 Select
Connected Multiviewer Project
.
3 Browse to a new, empty folder and click
Choose
.
Summary of Contents for UCP-3901
Page 1: ...User Manual 13 03084 010 M00 AB 2020 10 27 UCP 3901 UNIFIED COMPUTE PROCESSOR FOR DENSITÉ ...
Page 18: ...18 Introduction Supported SFP28 Cartridges ...
Page 32: ...32 UCP 3901 Card Installation and Operation Remote control using RollCall ...
Page 36: ...36 Connections and Cabling Cabling to Support SMPTE ST 2022 7 with a UCP 3901 ...
Page 122: ...122 Essence Processing SDC SFP Configuration ...
Page 202: ...202 Maintenance Troubleshooting Keep Fiber Connections Clean ...