Three-Phase UPS (10kVA-160kVA) Series
User Manual
5 Operation Guide
81
No.
Checking item
12
Check if the installation and wiring are good for system reformation, expansion and
maintenance in future.
5.1.2 UPS Test
UPS test: When switching off mains switch, it can simulate the situation that the mains is power off.
When the mains is power off, the AC/DC red indicator will turn on and the buzzer will beep slowly.
5.2 UPS Announcements
Before starting UPS, check whether load is proper. The load capacity shouldn't exceed rated
output capacity of UPS to avoid overload protection.
Don't regard ON/OFF button on the UPS panel as the power switch of load. Don't start UPS
frequently.
When UPS works steadily, it can turn on load. Some devices generate large current when startup,
and may lead to overload protection. It is better to start them first. Start the high-power devices
first and then the small-power devices. If you want to close UPS, turn off the load first.
Before starting UPS for the first time, perform checking before power on. If it is ok, power on
UPS. If UPS hasn’t been used for a long time, it need to perform checking before power on.
5.2.1 Start UPS
Step 1
Switch on bypass switch.
Power board starts working and touch screen begins initializing. About 10s later, the initialization is
finished, the panel and LED works normally.
Step 2
Switch on mains switch.
If mains input is normal, rectifier indicator will be on. About 15s later, the DC voltage has been
completely established
Step 3
Switch on external battery cabinet switch.