Commissioning is required prior to releasing equipment for production. The party
responsible shall insure that installation is complete and done correctly. Safety
systems should be tested and operators trained. At the time of commissioning, the
first Periodic Maintenance Inspection should be performed to familiarize personnel
with the equipment. See Section 5 - PROCESSING and Section 7 -
MAINTENANCE.
4-11.1
Setpoints of all safety interlocks shall be documented for future reference.
4-11.2
Supply piping shall be checked for leaks.
4-11.3
Personnel operating, maintaining or supervising shall be instructed and trained in
their job functions and be required to demonstrate an understanding of the
equipment, its operation and safe operating procedures including emergency
shutdown.
4-11.4
Equipment shall be operated in accordance with original design parameters.
4-11.5
Personnel operating, maintaining or supervising shall be informed of the danger of
removing, or rendering ineffective, safety devices.