14
WIRING
For 240V AC opener, plug the opener into mains power. Alternatively if the gate is to be hard-wired into 240V power, this must be
completed by a licensed electrician. Now go to programming section.
For 24V (Low Voltage) opener, connect the low-voltage power cord from the opener to the low-voltage power supply from the
transformer box MGTR3-120VA. Proceed to programming section.
COMMISSIONING THE GATE OPENER
13
ELECTRICAL SAFETY
12
To reduce the risk of SEVERE INJURY or DEATH:
• BEFORE installing the power wiring or control stations be sure to follow all specifications and warnings. Failure to do so
may result in SEVERE INJURY to persons and/or damage to the opener.
• ALL electrical connections MUST be made by a licensed electrician.
• DO NOT install any wiring or attempt to run the opener without consulting the wiring diagram.
• ALL power wiring should be on a dedicated circuit and well protected.
• ALL power and control wiring MUST be run in separate conduit.
• Disconnect power at the fuse box BEFORE proceeding.
• ANY maintenance to the opener or in the area near the opener MUST NOT be performed until disconnecting the electrical
power (AC and battery). Upon completion of maintenance the area MUST be cleared and secured, at that time the
unit may be returned to service.